- A
The project is on budget but behind schedule.
Why wrong: CPI<1 means over budget, not on budget.
- B
The project is over budget and ahead of schedule.
Why wrong: SPI<1 means behind schedule, not ahead.
- C
The project is under budget and ahead of schedule.
Why wrong: CPI and SPI less than 1 indicate over budget and behind schedule.
- D
The project is over budget and behind schedule.
CPI=0.8 (over budget), SPI=0.9 (behind schedule).
Quick Answer
The correct answer is that the project is over budget and behind schedule. This conclusion comes directly from interpreting earned value indices: a CPI of 0.8 means the project is earning only $0.80 for every dollar spent, indicating cost inefficiency and an over-budget condition, while an SPI of 0.9 means the project is progressing at 90% of the planned rate, signaling a schedule delay. On the CompTIA Project+ PK0-005 exam, this type of question tests your ability to read CPI and SPI values without calculation—a common trap is confusing values above 1.0 (good) with those below 1.0 (bad). Remember, both indices use 1.0 as the baseline: below 1.0 is trouble, above 1.0 is favorable. A handy memory tip is “Less than one? Underdone” — meaning under budget performance and under schedule progress.
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project is in the execution phase. The project manager discovers that the actual cost performance index (CPI) is 0.8 and the schedule performance index (SPI) is 0.9. What does this indicate about the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
The project is over budget and behind schedule.
A CPI of 0.8 means the project is earning only $0.80 for every $1.00 spent, indicating it is over budget. An SPI of 0.9 means the project is progressing at 90% of the planned rate, indicating it is behind schedule. Therefore, the project is both over budget and behind schedule, making option D correct.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The project is on budget but behind schedule.
Why it's wrong here
CPI<1 means over budget, not on budget.
- ✗
The project is over budget and ahead of schedule.
Why it's wrong here
SPI<1 means behind schedule, not ahead.
- ✗
The project is under budget and ahead of schedule.
Why it's wrong here
CPI and SPI less than 1 indicate over budget and behind schedule.
- ✓
The project is over budget and behind schedule.
Why this is correct
CPI=0.8 (over budget), SPI=0.9 (behind schedule).
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often confuse the direction of the index values, mistakenly thinking a CPI or SPI below 1.0 means under budget or ahead of schedule, when in fact values less than 1.0 indicate unfavorable performance (over budget or behind schedule).
Detailed technical explanation
How to think about this question
The Cost Performance Index (CPI) is calculated as Earned Value (EV) divided by Actual Cost (AC); a CPI below 1.0 indicates cost overrun. The Schedule Performance Index (SPI) is EV divided by Planned Value (PV); an SPI below 1.0 indicates schedule delay. In earned value management (EVM), these indices are used to forecast project completion costs and dates, with CPI and SPI trends often signaling the need for corrective action or re-baselining.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Concepts practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: The project is over budget and behind schedule. — A CPI of 0.8 means the project is earning only $0.80 for every $1.00 spent, indicating it is over budget. An SPI of 0.9 means the project is progressing at 90% of the planned rate, indicating it is behind schedule. Therefore, the project is both over budget and behind schedule, making option D correct.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 24, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.