Project Management Concepts →mediumMultiple Select

PK0-005 Project Management Concepts Practice Question

Which TWO of the following are key characteristics of a project? (Select TWO).

⚠ Common exam trap

The trap is selecting 'ongoing and repetitive' or 'permanent team' because those describe familiar work environments, but the exam expects strict PMBOK definitions where projects are temporary and unique.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Produces a unique product, service, or result

Option A is correct because a defining characteristic of a project is that it produces a unique product, service, or result, distinguishing it from repetitive operational work. Option E is correct because a project is a temporary endeavor with a defined beginning and end, undertaken to create that unique deliverable. Options B and D are incorrect because ongoing, repetitive activities and routine tasks describe operations, not projects. Option C is incorrect because project teams are typically temporary and disband upon project completion, rather than being permanent.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Produces a unique product, service, or result

    Why this is correct

    Uniqueness is a defining project characteristic: every project creates a distinct product, service, or result, differentiating it from routine operations. This progressive elaboration of a novel deliverable satisfies the stem's requirement for a key project characteristic.

  • ✗

    Ongoing and repetitive

    Why it's wrong here

    Projects are temporary endeavours with defined start and end dates, so ongoing repetitive work describes operations instead. Continuous, cyclical activity is the defining trait of business-as-usual processes, which is why this option is the operational counterpart rather than a project characteristic.

  • ✗

    Has a permanent team

    Why it's wrong here

    A project team is assembled for the duration of the initiative and disbanded at closure, so permanence contradicts the temporary nature of projects. Permanent teams belong to operational functions and departments, where staffing persists to sustain recurring service delivery rather than a finite deliverable.

  • ✗

    Involves routine tasks

    Why it's wrong here

    Projects deliver a unique product, service or result, so routine tasks repeated identically contradict that uniqueness. Routine work is characteristic of operations, where established procedures run continuously; project work instead involves novel, non-repetitive activities undertaken to achieve a specific objective.

  • ✓

    Temporary endeavor

    Why this is correct

    A project is a temporary endeavour with a defined start and end, dissolving once objectives are met. This satisfies the stem's request for a key characteristic, distinguishing projects from ongoing operations, which are continuous and have no predetermined completion date.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.