Courseiva
Tools and Documentation →hardMultiple Choice

PK0-005 Tools and Documentation Practice Question

A project is 60% complete. The original budget (BAC) is $200,000. Actual costs to date are $130,000, and the earned value is $120,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost efficiency?

⚠ Common exam trap

The trap is mixing up EAC formulas; candidates often apply EAC = AC + (BAC - EV) or simply add the variance to BAC, producing $210,000 or $230,000 instead of dividing BAC by CPI.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

$216,667

EAC is calculated using the formula EAC = BAC / CPI when the project is expected to continue at the current cost efficiency. Here CPI = EV / AC = 120,000 / 130,000 = 0.9231, so EAC = 200,000 / 0.9231 = $216,667. This matches option A and reflects the cost overrun trend observed to date.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    $216,667

    Why this is correct

    Dividing budget at completion by cost performance index ($200,000 ÷ ($120,000 ÷ $130,000)) yields $216,667. This satisfies the stem's constraint that the project continues at its current cost efficiency, so EAC is BAC ÷ CPI rather than a bottom-up re-estimate.

  • ✗

    $250,000

    Why it's wrong here

    This divides BAC by the earned-value percentage rather than by CPI, conflating schedule progress with cost performance. The current cost efficiency is $120,000 ÷ $130,000, giving roughly $216,667. Percentage-of-completion arithmetic belongs to independent EAC estimates, not the continuing-CPI formula the scenario specifies.

  • ✗

    $200,000

    Why it's wrong here

    Assuming the original budget equals the final cost ignores the $10,000 overspend already incurred: CPI is $120,000 ÷ $130,000, so the project is spending faster than it earns. BAC-based EAC applies only when remaining work is expected to proceed at planned cost efficiency, which the stem explicitly rules out.

  • ✗

    $230,000

    Why it's wrong here

    This applies the TCPI-style remaining-budget arithmetic, but EAC at current cost efficiency is BAC divided by CPI ($200,000 ÷ 0.923), giving roughly $216,667. The figure here instead adds the cost variance to BAC, which suits a one-off variance that will not recur, not the continuing-efficiency assumption stated.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.