Courseiva
Tools and DocumentationhardMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

A project is 60% complete. The original budget (BAC) is $200,000. Actual costs to date are $130,000, and the earned value is $120,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost efficiency?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

$216,667

Current CPI = EV/AC = 120,000/130,000 = 0.9231. EAC = BAC/CPI = 200,000 / 0.9231 ≈ $216,667. Alternatively, EAC = AC + (BAC - EV)/CPI = 130,000 + (80,000)/0.9231 ≈ $216,667.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • $216,667

    Why this is correct

    Correct: EAC = BAC/CPI = 200,000 / (120/130) = 216,667.

  • $250,000

    Why it's wrong here

    Not supported by calculations.

  • $200,000

    Why it's wrong here

    This is the original budget, not adjusted for current performance.

  • $230,000

    Why it's wrong here

    This might come from using incorrect formula.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.