Courseiva
Project Management ConceptsmediumMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

During project execution, the project team completes a deliverable that exceeds the specified requirements by adding extra features without authorization. This is an example of which concept?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Gold plating

Gold plating is when the team adds extra features beyond what was required, which can increase cost and risk without customer approval.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Gold plating

    Why this is correct

    Adding extra features beyond requirements is gold plating.

  • Scope creep

    Why it's wrong here

    Scope creep is uncontrolled changes to scope, often from stakeholders; gold plating is from the team.

  • Value analysis

    Why it's wrong here

    Value analysis is a technique to reduce cost while maintaining function.

  • Progressive elaboration

    Why it's wrong here

    Progressive elaboration is iterative refinement of the project plan.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.