easyMultiple ChoiceObjective-mapped
PK0-005 Practice Question: The primary difference between a risk and an…
What is the primary difference between a risk and an issue in project management?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
A risk is an uncertain future event; an issue is a current problem
A risk is an uncertain event that may happen in the future, while an issue is a current problem that has already occurred and needs resolution.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Risks are documented in the issue log; issues are documented in the risk register
Why it's wrong here
Risks go in the risk register; issues go in the issue log.
- ✓
A risk is an uncertain future event; an issue is a current problem
Why this is correct
Correct. Risk is future uncertainty; issue is a present reality.
- ✗
Risks are always negative; issues can be positive or negative
Why it's wrong here
Both risks and issues can be positive or negative.
- ✗
There is no difference; the terms are interchangeable
Why it's wrong here
They are distinct concepts in project management.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.