PK0-005 Project Life Cycle Practice Question
A project manager is developing a communication plan. Which two factors should be considered for each stakeholder? (Select TWO.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Communication needs
Communication needs and preferred frequency are key inputs to the communication plan.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Vendor performance
Why it's wrong here
Vendor performance is not a stakeholder communication factor.
- ✓
Communication needs
Why this is correct
Understanding what information stakeholders need is essential.
- ✗
Budget constraints
Why it's wrong here
Budget is not directly a factor in communication needs per stakeholder.
- ✗
Risk tolerance
Why it's wrong here
Risk tolerance is part of risk management, not communication planning.
- ✓
Preferred frequency
Why this is correct
How often stakeholders want updates is a key factor.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.