A project manager is developing a communication plan. Which two factors should be considered for each stakeholder? (Select TWO.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Communication needs

Communication needs and preferred frequency are key inputs to the communication plan.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Vendor performance

    Why it's wrong here

    Vendor performance is not a stakeholder communication factor.

  • Communication needs

    Why this is correct

    Understanding what information stakeholders need is essential.

  • Budget constraints

    Why it's wrong here

    Budget is not directly a factor in communication needs per stakeholder.

  • Risk tolerance

    Why it's wrong here

    Risk tolerance is part of risk management, not communication planning.

  • Preferred frequency

    Why this is correct

    How often stakeholders want updates is a key factor.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.