Courseiva
Project Life CyclehardMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

During the planning phase, a project manager is creating the WBS. Which of the following best describes the process of breaking down deliverables into smaller, more manageable components?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Decomposition

Decomposition is the process of breaking down deliverables into smaller work packages within the WBS.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Decomposition

    Why this is correct

    Decomposition is the correct term for breaking down deliverables into work packages.

  • Rolling wave planning

    Why it's wrong here

    Rolling wave planning involves progressive elaboration, but not specifically decomposition.

  • Analogous estimating

    Why it's wrong here

    Analogous estimating is a cost estimation technique.

  • Precedence diagramming

    Why it's wrong here

    Precedence diagramming is used for schedule network diagrams.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.