Courseiva
Project Management Concepts →mediumMultiple Choice

PK0-005 Project Management Concepts Practice Question

A project has a budget of $100,000 and a duration of 12 months. After 6 months, the project is 50% complete and has spent $60,000. What is the cost variance?

⚠ Common exam trap

The trap is confusing CV with 'budget remaining' or forgetting the sign convention — candidates often compute budget minus AC and get −$40,000, or drop the negative and pick $10,000, when the correct formula is EV − AC.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

-$10,000

Cost variance (CV) = Earned Value (EV) − Actual Cost (AC). At 6 months with a $100,000 budget and 50% completion, EV = 0.50 × $100,000 = $50,000. AC = $60,000. CV = $50,000 − $60,000 = −$10,000, indicating the project is $10,000 over budget.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    -$10,000

    Why this is correct

    Cost variance is earned value minus actual cost. At 50% completion, earned value is $50,000, while actual cost is $60,000, giving $50,000 − $60,000 = −$10,000. The negative result confirms the project is over budget at the six-month mark.

  • ✗

    -$40,000

    Why it's wrong here

    Cost variance is EV minus AC: $50,000 earned value minus $60,000 actual cost equals -$10,000, not -$40,000. Subtracting actual cost from total budget ignores earned value; that figure answers a different question about remaining budget, not variance.

  • ✗

    $10,000

    Why it's wrong here

    Cost variance is EV minus AC: $50,000 minus $60,000 equals -$10,000, so a positive $10,000 is wrong. It tempts as the absolute overspend, but variance is signed; the positive value would be correct only if actual cost were below earned value.

  • ✗

    $40,000

    Why it's wrong here

    Cost variance is EV minus AC: $50,000 minus $60,000 equals -$10,000, not $40,000. That figure is the remaining budget ($100,000 minus $60,000), which tempts because it uses the same inputs, but it measures funds left, not schedule-adjusted variance.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.