PK0-005 Practice Question: A project manager is creating a work breakdown…

A project manager is creating a work breakdown structure (WBS) for a software development project. Which technique is most effective for decomposing the project scope into manageable components?

⚠ Common exam trap

PK0-005 often tests whether candidates confuse WBS construction techniques (decomposition) with estimating techniques (analogous, bottom-up, parametric) or scheduling techniques (rolling wave), so the trap is picking a familiar-sounding estimating term when the question asks how scope is broken down.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Decomposition

Decomposition is the actual PMBOK technique used to break down project scope and deliverables into smaller, more manageable work packages within the WBS. It is the tool and technique listed under the 'Create WBS' process, applied iteratively until work packages are at a level where they can be estimated, scheduled, and assigned. The other options are estimating or scheduling techniques, not WBS construction techniques.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Bottom-up estimating

    Why it's wrong here

    Bottom-up estimating aggregates cost or effort from the lowest-level components upward; it produces estimates, not the hierarchical decomposition itself, so it cannot create the WBS structure. It is tempting because it follows decomposition and improves accuracy, and it would be the correct technique when costing already-defined work packages.

  • ✗

    Rolling wave planning

    Why it's wrong here

    Rolling wave planning progressively elaborates near-term work packages while deferring distant detail, so it does not fully decompose the entire project scope into a complete WBS hierarchy. It is tempting because it suits long, uncertain projects, and it would be the correct technique when detailed planning of later phases must wait for more information.

  • ✗

    Analogous estimating

    Why it's wrong here

    Analogous estimating derives duration or cost from comparable past projects; it does not decompose scope into deliverables. WBS creation requires decomposition techniques such as top-down or work-package breakdown. Analogous estimating would suit early-stage effort forecasting when historical data exists, not scope definition.

  • ✓

    Decomposition

    Why this is correct

    Decomposition subdivides project scope and deliverables into progressively smaller, manageable work packages, which is the recognised WBS technique. It directly satisfies the stem's requirement to break scope into manageable components, unlike alternatives such as brainstorming or expert judgement that generate ideas rather than structure scope.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.