PK0-005 Project Management Concepts Practice Question
A project manager is defining the roles and responsibilities for a project. Which TWO of the following are typical responsibilities of the project sponsor? (Select TWO).
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Act as a champion for the project
The sponsor provides resources and champions the project; the PM does planning and execution.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Act as a champion for the project
Why this is correct
Sponsor champions the project at executive level.
- ✗
Perform quality control inspections
Why it's wrong here
Quality control is often done by team members or QA.
- ✗
Assign tasks to team members
Why it's wrong here
Task assignment is typically done by PM or team lead.
- ✗
Develop the project schedule
Why it's wrong here
Developing schedule is PM responsibility.
- ✓
Provide financial resources and budget approval
Why this is correct
Sponsor secures funding and approves budget.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.