PK0-005 Practice Question: A project manager documents a change request and…

A project manager documents a change request and updates the change log. Which step of integrated change control is being performed?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Change request documentation and logging

Documenting the change and updating the change log is performed when the change request is first submitted and logged. This is the 'Change Request Documentation and Logging' step of integrated change control, which occurs prior to CCB review and approval.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Updating project plan

    Why it's wrong here

    Plan update occurs after approval.

  • Evaluating impact

    Why it's wrong here

    Evaluation comes before documentation.

  • Change request documentation and logging

    Why this is correct

    Correct action described.

  • CCB review

    Why it's wrong here

    CCB reviews the request, not just documentation.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.