During which project phase is the project charter typically created and approved?

⚠ Common exam trap

The trap is confusing the charter with the project management plan or assuming it is created during Planning—candidates must remember the charter is an Initiating output that precedes all planning.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Initiating

The project charter is created and approved during the Initiating phase, where the project is formally authorized and the project manager is assigned authority. It documents the high-level scope, objectives, stakeholders, and constraints, serving as the project's formal authorization. Planning, executing, and closing phases occur after the charter exists.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Initiating

    Why this is correct

    The project charter is produced during Initiating, where the project is formally authorised and the project manager is assigned. Approval of the charter marks the phase boundary, giving the project its mandate before planning begins.

  • ✗

    Closing

    Why it's wrong here

    Closing covers final deliverable handover, contract closure and releasing resources, by which point the charter was approved long ago. It is tempting because closure also produces formal documentation, but the charter authorises the project and is created during initiation, before planning begins.

  • ✗

    Executing

    Why it's wrong here

    Executing is when the charter's authorised work is delivered, so the document already exists and is baselined. It is tempting because executing is where the project manager spends most time, but charter creation and approval occur during initiation, before planning or execution begins.

  • ✗

    Planning

    Why it's wrong here

    Planning follows initiation, so the charter is already approved and used as input to the project management plan. It is tempting because planning produces most project documents, but the charter is an initiation output that formally authorises the project and the project manager.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.