During which project phase is the project charter typically created and approved?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Initiating

The project charter is created during the Initiating phase to formally authorize the project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Initiating

    Why this is correct

    The charter is created in the Initiating phase to authorize the project.

  • Closing

    Why it's wrong here

    Closing finalizes the project and archives documents.

  • Executing

    Why it's wrong here

    Executing involves performing the work defined in the plan.

  • Planning

    Why it's wrong here

    Planning occurs after initiation and uses the charter as input.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.