PK0-005 Project Life Cycle Practice Question
During which project phase is the project charter typically created and approved?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Initiating
The project charter is created during the Initiating phase to formally authorize the project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Initiating
Why this is correct
The charter is created in the Initiating phase to authorize the project.
- ✗
Closing
Why it's wrong here
Closing finalizes the project and archives documents.
- ✗
Executing
Why it's wrong here
Executing involves performing the work defined in the plan.
- ✗
Planning
Why it's wrong here
Planning occurs after initiation and uses the charter as input.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.