A project team discovers a problem that is currently happening and affecting project deliverables. The project manager needs to document this situation. Which document should be used to record this?

⚠ Common exam trap

PK0-005 often tests the risk-vs-issue distinction — candidates pick risk register because the problem sounds like a risk, but the question says it is 'currently happening,' which makes it an issue.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Issue log

An issue log records problems that have already occurred and are currently affecting the project, along with ownership, status, and resolution actions. Since the problem is 'currently happening and affecting deliverables,' it is an active issue, not a future risk, so it belongs in the issue log. The project manager documents it there to track resolution and communicate impact.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Change log

    Why it's wrong here

    A change log records approved changes to baselines and their implementation status, not the identification and tracking of an active problem. It would be correct when documenting a requested or implemented change, whereas an issue log captures problems currently affecting deliverables.

  • ✗

    Risk register

    Why it's wrong here

    A risk register holds uncertain future events with probability and impact ratings, not problems that have already materialised. It would be correct for identifying potential threats during planning, whereas an issue log documents current problems affecting deliverables.

  • ✓

    Issue log

    Why this is correct

    An issue log records problems that have already occurred and are currently affecting project deliverables, tracking ownership, status and resolution. It is the correct document here, whereas a risk log captures potential future events and a change request formally modifies baselined scope.

  • ✗

    Lessons learned

    Why it's wrong here

    Lessons learned are compiled at project or phase closure to improve future projects, so they cannot track a problem that is still occurring. They would be correct retrospectively, after the issue is resolved, whereas an issue log records active problems affecting deliverables.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.