PK0-005 A project is behind schedule Practice Question

A project is behind schedule. The project manager decides to start the testing phase before the development phase is completely finished. This is an example of which schedule compression technique?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Fast-tracking

Fast-tracking involves overlapping sequential activities to compress the schedule, but it increases risk of rework.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Crashing

    Why it's wrong here

    Crashing adds resources to critical path activities to reduce duration.

  • Resource leveling

    Why it's wrong here

    Resource leveling adjusts start and finish dates to manage resource constraints.

  • Fast-tracking

    Why this is correct

    Correct. Overlapping phases is fast-tracking.

  • Monte Carlo simulation

    Why it's wrong here

    Monte Carlo simulation is a quantitative risk analysis technique.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.