PK0-005 A project is behind schedule Practice Question
A project is behind schedule. The project manager decides to start the testing phase before the development phase is completely finished. This is an example of which schedule compression technique?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Fast-tracking
Fast-tracking involves overlapping sequential activities to compress the schedule, but it increases risk of rework.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Crashing
Why it's wrong here
Crashing adds resources to critical path activities to reduce duration.
- ✗
Resource leveling
Why it's wrong here
Resource leveling adjusts start and finish dates to manage resource constraints.
- ✓
Fast-tracking
Why this is correct
Correct. Overlapping phases is fast-tracking.
- ✗
Monte Carlo simulation
Why it's wrong here
Monte Carlo simulation is a quantitative risk analysis technique.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.