Question 816 of 1,000
Tools and DocumentationmediumMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

This PK0-005 practice question tests your understanding of tools and documentation. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project has a planned value (PV) of $50,000, earned value (EV) of $40,000, and actual cost (AC) of $45,000. What is the schedule variance (SV) and cost variance (CV)?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

SV = -$10,000, CV = -$5,000

Schedule variance (SV) is calculated as EV - PV = $40,000 - $50,000 = -$10,000, indicating the project is behind schedule. Cost variance (CV) is EV - AC = $40,000 - $45,000 = -$5,000, indicating the project is over budget. Option D correctly states both negative variances.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • SV = -$5,000, CV = -$10,000

    Why it's wrong here

    Values are swapped; SV is EV-PV, CV is EV-AC.

  • SV = -$10,000, CV = $5,000

    Why it's wrong here

    CV would be positive only if EV > AC, but here EV < AC.

  • SV = $10,000, CV = $5,000

    Why it's wrong here

    Positive variances would indicate ahead of schedule and under budget, which is not the case.

  • SV = -$10,000, CV = -$5,000

    Why this is correct

    Correct: SV negative indicates behind schedule; CV negative indicates over budget.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse the formulas for SV and CV, swapping the order of subtraction (e.g., using PV - EV for SV or AC - EV for CV), leading to incorrect positive values instead of the correct negative ones.

Detailed technical explanation

How to think about this question

In earned value management (EVM), SV measures schedule performance against the planned value baseline, while CV measures cost efficiency against actual costs. A negative SV means less work was completed than planned, and a negative CV means more money was spent than budgeted for the work accomplished. In real-world projects, these metrics are used to forecast estimate at completion (EAC) and identify corrective actions.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Tools and Documentation — This question tests Tools and Documentation — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: SV = -$10,000, CV = -$5,000 — Schedule variance (SV) is calculated as EV - PV = $40,000 - $50,000 = -$10,000, indicating the project is behind schedule. Cost variance (CV) is EV - AC = $40,000 - $45,000 = -$5,000, indicating the project is over budget. Option D correctly states both negative variances.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.