Project Life Cycle →easyMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project manager is in the process of developing the project charter. Which of the following would be included in the project charter?

⚠ Common exam trap

PK0-005 often tests the timing of project documents — the trap is selecting artifacts that sound important (risk register, WBS, EVM) but actually belong to later process groups, not the charter.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

High-level project objectives and constraints

The project charter is a high-level document that formally authorizes the project and gives the project manager authority to proceed. It contains the project purpose, measurable objectives, high-level requirements, assumptions, constraints, and a summary budget and milestone schedule. High-level objectives and constraints are core charter elements because they define what success looks like and the boundaries within which the project must operate.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    High-level project objectives and constraints

    Why this is correct

    The project charter formally authorises the project and records high-level objectives and constraints, giving the project manager authority to proceed. These elements define what the project must achieve and the boundaries within which it must operate.

  • ✗

    Earned value metrics

    Why it's wrong here

    Earned value metrics require a baselined schedule and cost, which the charter precedes. It is tempting because the charter authorises budget, but earned value analysis is an execution and monitoring activity, not content of the initiating document.

  • ✗

    Risk register with probability and impact matrix

    Why it's wrong here

    The risk register and probability-impact matrix are built during risk planning, once the charter exists. It is tempting because the charter lists high-level risks, but the structured register with scored probability and impact is a planning artefact, not a charter component.

  • ✗

    Detailed work breakdown structure

    Why it's wrong here

    The work breakdown structure decomposes scope into deliverables during planning, after the charter authorises the project. It is tempting because it defines scope, but it belongs to the planning phase, whereas the charter contains the high-level scope description and project boundaries.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.