Ensure each element is a deliverable
The WBS should be decomposed to work packages, and each element should represent a deliverable, not an activity.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Ensure each element is a deliverable
Why this is correct
WBS focuses on deliverables.
- ✓
Decompose to work packages
Why this is correct
Work packages are the lowest level.
- ✗
Assign durations to elements
Why it's wrong here
Durations are assigned in schedule management.
- ✗
Include project activities
Why it's wrong here
WBS is deliverable-oriented, not activity-oriented.
- ✗
Include only high-level scope
Why it's wrong here
WBS should be detailed.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.