Project Life CyclemediumMultiple SelectObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager is creating a WBS. Which two best practices should be followed? (Select TWO)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Ensure each element is a deliverable

The WBS should be decomposed to work packages, and each element should represent a deliverable, not an activity.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ensure each element is a deliverable

    Why this is correct

    WBS focuses on deliverables.

  • Decompose to work packages

    Why this is correct

    Work packages are the lowest level.

  • Assign durations to elements

    Why it's wrong here

    Durations are assigned in schedule management.

  • Include project activities

    Why it's wrong here

    WBS is deliverable-oriented, not activity-oriented.

  • Include only high-level scope

    Why it's wrong here

    WBS should be detailed.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.