Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: A project requires a specific software library…

A project requires a specific software library that is only available from a single vendor. The vendor's delivery schedule dictates when the project can begin integration testing. This dependency is best described as:

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

External dependency

An external dependency is one outside the project's control.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Resource constraint

    Why it's wrong here

    Resource constraints refer to limited availability of resources, not external dependencies.

  • External dependency

    Why this is correct

    The dependency on an external vendor's schedule is an external dependency.

  • Mandatory dependency

    Why it's wrong here

    Mandatory dependencies are inherent in the work, often physical or logical, but this is outside the project's control.

  • Discretionary dependency

    Why it's wrong here

    Discretionary dependencies are best practice but can be changed.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.