Courseiva

PK0-005 Project Management Concepts Practice Question

During project execution, a key stakeholder requests additional features that were not originally approved. The project manager is concerned about scope creep. Which type of project constraint is most directly impacted by scope creep?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Scope

Scope creep refers to uncontrolled changes or continuous growth in a project's scope. This directly impacts the scope constraint, and typically affects cost and schedule as well. However, scope is the primary constraint impacted.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Quality

    Why it's wrong here

    Quality is affected only after added work is accepted without adjusting resources or time; scope creep directly alters the scope baseline, not quality metrics. Quality is tempting because unmanaged additions often erode testing and standards, and quality management would be the correct focus when validating deliverables against defined acceptance criteria.

  • ✗

    Schedule

    Why it's wrong here

    Scope creep adds unapproved work, which consumes the schedule baseline's float and milestones; the constraint directly impacted is scope itself, with schedule affected only indirectly. Schedule is tempting because added features do take time, and schedule management would be the correct focus when a change request has been approved and dates must be renegotiated.

  • ✓

    Scope

    Why this is correct

    Scope creep adds unapproved features, directly expanding the agreed deliverables and work content. The scope constraint, defined by the approved scope baseline, is therefore the constraint most immediately impacted, since the change alters what the project must deliver.

  • ✗

    Cost

    Why it's wrong here

    Cost is affected only indirectly: added features consume budget once effort grows, but the constraint directly breached is scope itself. Cost would be the answer if the question asked which constraint the additional funding demand impacts.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.