Courseiva
Project Life CycleeasyMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager is developing the project charter. Which of the following should be included as a key element of the project charter?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

High-level budget and schedule

The project charter formally authorizes the project and includes the project purpose, objectives, high-level scope, budget, schedule, assumptions, constraints, and the authority of the project manager. The other options are developed later in the planning or executing phases.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • High-level budget and schedule

    Why this is correct

    The project charter contains high-level budget and schedule estimates.

  • Detailed risk response plan

    Why it's wrong here

    Detailed risk responses are part of the risk management plan created during planning.

  • Work Breakdown Structure

    Why it's wrong here

    The WBS is created during the planning phase, not included in the project charter.

  • Communication management plan

    Why it's wrong here

    The communication plan is developed during the planning phase.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.