- A
Change log
The change log records all change requests and their status.
- B
Status report
Why wrong: The status report is updated after the change is implemented, not immediately.
- C
Risk register
Why wrong: The risk register is updated only if the change affects risks.
- D
Project baseline
The baseline must be updated to reflect the approved change.
- E
Stakeholder register
Why wrong: The stakeholder register is not automatically updated with every change.
Quick Answer
The answer is the change log and the project baseline. These two documents must be updated when a change request is approved because the change log provides the official audit trail, recording the approval decision, implementation steps, and closure details, while the project baseline—whether scope, schedule, or cost—must be revised to reflect the approved change so that all future work and variance analysis are measured against the new baseline. On the CompTIA Project+ PK0-005 exam, this concept tests your understanding of the integrated change control process, often appearing in scenario-based questions where a trap answer lists the project management plan instead of the baseline itself. Remember, the plan describes how to manage changes, but the baseline is what actually gets updated to capture the new approved scope or budget. A helpful memory tip: “Log the approval, baseline the change”—the log tracks the decision, the baseline locks in the new target.
PK0-005 Tools and Documentation Practice Question
This PK0-005 practice question tests your understanding of tools and documentation. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which TWO documents should be updated when a change request is approved?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Change log
The change log is updated to record the approval, implementation details, and closure of the change request, providing an audit trail. The project baseline (e.g., scope, schedule, cost) must be updated to reflect the approved change, ensuring all future work and variance analysis are measured against the revised baseline.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Change log
Why this is correct
The change log records all change requests and their status.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Status report
Why it's wrong here
The status report is updated after the change is implemented, not immediately.
- ✗
Risk register
Why it's wrong here
The risk register is updated only if the change affects risks.
- ✓
Project baseline
Why this is correct
The baseline must be updated to reflect the approved change.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Stakeholder register
Why it's wrong here
The stakeholder register is not automatically updated with every change.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates confuse the risk register with the change log, thinking that all approved changes automatically update the risk register, when in fact the risk register is only updated if the change introduces or modifies a specific risk.
Detailed technical explanation
How to think about this question
In project management, the change log is a formal record of all change requests, including their status (e.g., submitted, approved, rejected) and implementation details. The project baseline (often managed through a configuration management system) is the approved version of the project management plan plus subsidiary plans; updating it ensures that performance measurement baselines (e.g., schedule baseline, cost baseline) remain valid after an approved change. Failure to update the baseline can lead to inaccurate earned value management (EVM) calculations and scope creep.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Tools and Documentation — study guide chapter
Learn the concepts, then practise the questions
- →
Tools and Documentation practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Tools and Documentation — This question tests Tools and Documentation — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Change log — The change log is updated to record the approval, implementation details, and closure of the change request, providing an audit trail. The project baseline (e.g., scope, schedule, cost) must be updated to reflect the approved change, ensuring all future work and variance analysis are measured against the revised baseline.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more ways this is tested on PK0-005
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. A project manager is reviewing a change request that has been approved. The change will affect the project scope, schedule, and budget. Which document should the project manager update first to ensure all changes are captured and communicated?
hard- ✓ A.Change log
- B.Scope statement
- C.Project management plan
- D.Schedule baseline
Why A: The change log is the official repository for recording all approved change requests, including their details and impacts. Updating it first ensures that the change is formally documented and communicated to stakeholders before any baselines or plans are modified. This aligns with the integrated change control process, where the change log serves as the primary communication tool for change status.
Keep practising
More PK0-005 practice questions
- A project team is working on a software development project and needs to track changes to requirements, design documents…
- Arrange the steps for conducting a quality audit.
- Arrange the steps for initiating a project in the correct order.
- Put the steps for closing a project in the correct order.
- Put the steps for creating a work breakdown structure (WBS) in the correct order.
- Put the steps for managing a change request in the correct order.
Last reviewed: Jun 24, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.