PK0-005 Project Management Concepts Practice Question
A steering committee is reviewing project performance. Which of the following is a key responsibility of the steering committee?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Approving changes to the project scope
The steering committee provides governance, approves major changes, and ensures alignment with business objectives.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Assigning daily tasks to team members
Why it's wrong here
This is the PM's responsibility.
- ✓
Approving changes to the project scope
Why this is correct
The steering committee typically approves significant changes.
- ✗
Developing the project schedule
Why it's wrong here
Scheduling is done by the PM and team.
- ✗
Resolving technical issues
Why it's wrong here
Technical issues are resolved by the team.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.