PK0-005 Project Management Concepts Practice Question

A steering committee is reviewing project performance. Which of the following is a key responsibility of the steering committee?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Approving changes to the project scope

The steering committee provides governance, approves major changes, and ensures alignment with business objectives.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Assigning daily tasks to team members

    Why it's wrong here

    Daily task allocation belongs to the project manager or team lead, not the governance board. The steering committee provides strategic direction, approves funding and arbitrates escalated decisions. It is tempting because the committee does assign ownership of actions, but that is at project level, not individual daily work.

  • ✓

    Approving changes to the project scope

    Why this is correct

    Scope changes alter the approved baseline, so only the steering committee holds the authority to authorise them. This governance body owns the project charter and budget, satisfying the stem's need for the group accountable for approving modifications to project scope.

  • ✗

    Developing the project schedule

    Why it's wrong here

    Schedule development is a project management activity performed by the project manager using scheduling tools. The steering committee approves the resulting baseline and resolves escalated conflicts. It is tempting because the committee approves the schedule, but approval differs from the hands-on construction of activities, dependencies and durations.

  • ✗

    Resolving technical issues

    Why it's wrong here

    Technical issues are resolved by the project team and technical leads, not escalated to governance. The steering committee's remit is strategic oversight: approving scope, budget and major risks. It is tempting because escalation paths exist, but technical troubleshooting sits outside that governance layer.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.