A steering committee is reviewing project performance. Which of the following is a key responsibility of the steering committee?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Approving changes to the project scope

The steering committee provides governance, approves major changes, and ensures alignment with business objectives.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Assigning daily tasks to team members

    Why it's wrong here

    This is the PM's responsibility.

  • Approving changes to the project scope

    Why this is correct

    The steering committee typically approves significant changes.

  • Developing the project schedule

    Why it's wrong here

    Scheduling is done by the PM and team.

  • Resolving technical issues

    Why it's wrong here

    Technical issues are resolved by the team.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.