PK0-005 Project Management Concepts Practice Question
Which of the following is NOT a phase in the typical project life cycle?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Testing
The typical phases are initiating, planning, executing, monitoring and controlling, and closing. 'Testing' is not a phase; it is an activity within executing.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Testing
Why this is correct
Testing is an activity, not a life cycle phase.
- ✗
Monitoring and controlling
Why it's wrong here
It is a phase.
- ✗
Closing
Why it's wrong here
It is a phase.
- ✗
Initiating
Why it's wrong here
It is a phase.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.