Courseiva
Project Management ConceptseasyMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

Which of the following is NOT a phase in the typical project life cycle?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Testing

The typical phases are initiating, planning, executing, monitoring and controlling, and closing. 'Testing' is not a phase; it is an activity within executing.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Testing

    Why this is correct

    Testing is an activity, not a life cycle phase.

  • Monitoring and controlling

    Why it's wrong here

    It is a phase.

  • Closing

    Why it's wrong here

    It is a phase.

  • Initiating

    Why it's wrong here

    It is a phase.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.