PK0-005 Project Life Cycle Practice Question

A project is transitioning from the planning phase to the executing phase. The project manager must ensure the team is prepared to begin work. Which THREE activities should be performed during this transition? (Choose three.)

⚠ Common exam trap

The trap here is mixing closing-phase activities, such as contract closure and final inspections, into the planning-to-executing transition.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Obtain formal approval of the project management plan.

The transition from planning to executing requires the plan to be formally approved, the team to be acquired and assigned, and a kickoff to align everyone. Closing contracts and final quality inspections belong to later phases or to specific contract completion points, so they are not part of this transition.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Obtain formal approval of the project management plan.

    Why this is correct

    Execution should not begin until the project management plan is approved by the sponsor or governance authority. Formal approval confirms that scope, schedule, cost, and other baselines are accepted and that the project manager is authorized to proceed. Without this approval, the team could start work against an unapproved plan.

  • ✗

    Close all procurement contracts from the planning phase.

    Why it's wrong here

    Procurement contracts are typically closed at the end of the project or when a contract's work is complete, not when transitioning to execution. Closing them prematurely would terminate vendor support needed during execution. This activity belongs to the closing phase or to contract completion, not to the planning-to-executing transition.

  • ✓

    Acquire the project team and assign resources to activities.

    Why this is correct

    Acquiring the team and assigning resources ensures the people needed to perform the work are available when execution starts. This activity confirms availability, skills, and reporting relationships. It is a key transition step because execution depends on having the right resources in place before work packages begin.

  • ✓

    Conduct a kickoff meeting to align the team and stakeholders.

    Why this is correct

    The kickoff meeting marks the start of execution by communicating the project plan, roles, and expectations to the team and stakeholders. It builds shared understanding and commitment before work begins. This is a standard transition activity that aligns everyone with the approved plan and reduces ambiguity during the executing phase.

  • ✗

    Perform a final quality inspection of all deliverables.

    Why it's wrong here

    Final quality inspections occur during or at the end of execution when deliverables are produced, not before execution begins. At the transition point, deliverables do not yet exist. Quality planning and quality assurance activities may start, but final inspection is a later activity tied to verifying completed work.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.