A project manager is closing a project. Which TWO activities are typically performed during the closing phase?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Obtaining formal acceptance from the sponsor
Closing activities include obtaining formal acceptance from the sponsor and archiving project documents. Releasing resources and lessons learned are also part of closing, but the question asks for exactly two.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Performing earned value analysis
Why it's wrong here
Earned value analysis occurs during monitoring and controlling.
- ✗
Creating the risk register
Why it's wrong here
The risk register is created during planning.
- ✓
Obtaining formal acceptance from the sponsor
Why this is correct
Formal acceptance confirms the project is complete.
- ✓
Archiving project documents
Why this is correct
Archiving preserves project records for future use.
- ✗
Developing the project charter
Why it's wrong here
The project charter is created during initiating.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.