A project has a CPI of 0.9 and an SPI of 1.1. Which two statements are true? (Select TWO.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is ahead of schedule.

CPI < 1 means over budget; SPI > 1 means ahead of schedule.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is on schedule.

    Why it's wrong here

    On schedule would have SPI = 1.

  • The project is ahead of schedule.

    Why this is correct

    SPI > 1 indicates ahead of schedule.

  • The project is under budget.

    Why it's wrong here

    Under budget would have CPI > 1.

  • The project is behind schedule.

    Why it's wrong here

    Behind schedule would have SPI < 1.

  • The project is over budget.

    Why this is correct

    CPI < 1 indicates cost overrun.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.