PK0-005 Project Life Cycle Practice Question
A project has a CPI of 0.9 and an SPI of 1.1. Which two statements are true? (Select TWO.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The project is ahead of schedule.
CPI < 1 means over budget; SPI > 1 means ahead of schedule.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The project is on schedule.
Why it's wrong here
On schedule would have SPI = 1.
- ✓
The project is ahead of schedule.
Why this is correct
SPI > 1 indicates ahead of schedule.
- ✗
The project is under budget.
Why it's wrong here
Under budget would have CPI > 1.
- ✗
The project is behind schedule.
Why it's wrong here
Behind schedule would have SPI < 1.
- ✓
The project is over budget.
Why this is correct
CPI < 1 indicates cost overrun.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.