Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Change Control Process Practice Question

Exhibit

Refer to the exhibit.

Change Request Log
ID | Description | Status | Priority | Impact
CR-001 | Add new module | Approved | High | Schedule +2 weeks, Cost +$5k
CR-002 | Reduce testing | Rejected | Low | N/A
CR-003 | Change vendor | Pending | Medium | Schedule -1 week, Cost -$2k
CR-004 | UI redesign | Approved | High | Schedule +4 weeks, Cost +$10k

A project manager reviews the following change request log: - CR-001: Adds 2 weeks to the schedule. - CR-002: Low-priority enhancement; no schedule impact. - CR-003: Reduces schedule by 1 week to offset delays from other changes. - CR-004: Urgent but high-risk; could cause additional delays. Based on the change request log, which of the following actions should the project manager take to maintain the project schedule?

⚠ Common exam trap

Examine the schedule impact of each change request before approving; even positive impacts should be evaluated for risk.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Approve CR-003

Based on the change request log, CR-001 adds 2 weeks to the schedule, CR-002 is a low-priority enhancement with no schedule impact, CR-003 reduces the schedule by 1 week to offset delays from other changes, and CR-004 is an urgent but high-risk change that could cause additional delays. To maintain the project schedule, the project manager should approve CR-003 because it directly reduces the schedule and helps compensate for delays caused by approved changes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Implement CR-004 immediately

    Why it's wrong here

    Implementing CR-004 immediately is risky; it may introduce additional delays and negatively impact the schedule.

  • Approve CR-003

    Why this is correct

    Approving CR-003, which reduces the schedule by one week, is the best action to offset delays and maintain the schedule.

  • Prioritize CR-002

    Why it's wrong here

    Prioritizing CR-002 is not effective because it has no schedule impact and does not address existing delays.

  • Reject CR-001

    Why it's wrong here

    Rejecting CR-001 may not be the best course if it is critical to project scope; the question asks for actions to maintain schedule, and approving a beneficial change is more direct.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.