Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: During project execution, a team member reports…

During project execution, a team member reports that a key deliverable will be delayed by two weeks due to an unforeseen technical issue. The project manager evaluates the change and determines the impact on the critical path. According to best practices, what should the project manager do first?

⚠ Common exam trap

Test-takers frequently confuse 'immediate communication' (Option D) with the correct first step, failing to recognize that formal impact analysis and a change request must precede any stakeholder notification or budget requests.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analyze the impact on the project schedule and cost, then submit a change request.

Upon identifying a delay that impacts the critical path, the project manager must first analyze the full impact on schedule and cost before formally documenting the change. Submitting a change request initiates the formal change control process, ensuring that all stakeholders review and approve adjustments before any plan updates or actions are taken. This aligns with the PMBOK Guide's integrated change control process, which requires impact analysis as the first step after identifying a potential change.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the project plan and inform stakeholders after the delay occurs.

    Why it's wrong here

    Stakeholders should be informed early, and a change request should be made before updating plans.

  • Tell the team member to work overtime to meet the original deadline.

    Why it's wrong here

    This ignores the issue and does not follow change management.

  • Analyze the impact on the project schedule and cost, then submit a change request.

    Why this is correct

    Standard change control process: assess impact, then request change.

  • Immediately inform the sponsor and request a budget increase.

    Why it's wrong here

    This jumps to action without proper analysis and change control.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.