Courseiva
Project Life CyclemediumMultiple SelectObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.2. Which TWO conclusions can be drawn? (Select TWO.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is ahead of schedule

CPI < 1 means over budget; SPI > 1 means ahead of schedule. EAC > BAC typically when CPI < 1, and TCPI to meet BAC is >1.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is on schedule and on budget

    Why it's wrong here

    Both indices are not 1.

  • The project is ahead of schedule

    Why this is correct

    Correct: SPI=1.2 > 1 indicates ahead of schedule.

  • The project is under budget

    Why it's wrong here

    CPI < 1 means over budget.

  • The project is behind schedule

    Why it's wrong here

    SPI > 1 means ahead of schedule.

  • The project is over budget

    Why this is correct

    Correct: CPI=0.8 < 1 indicates over budget.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.