Courseiva
Project Life Cycle →mediumMultiple Select

PK0-005 Project Life Cycle Practice Question

A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.2. Which TWO conclusions can be drawn? (Select TWO.)

⚠ Common exam trap

The trap is inverting the CPI and SPI thresholds — candidates forget that values below 1.0 are bad (over budget / behind schedule) and values above 1.0 are good (under budget / ahead of schedule).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The project is ahead of schedule

Option B is correct because an SPI of 1.2 is greater than 1.0, which indicates that the project is ahead of schedule, as earned value exceeds planned value. Option E is correct because a CPI of 0.8 is less than 1.0, which indicates that the project is over budget, as the cost of work performed exceeds the earned value. Option A is incorrect because the project is neither on schedule nor on budget, given SPI > 1 and CPI < 1. Option C is incorrect because a CPI below 1.0 means the project is over budget, not under budget. Option D is incorrect because an SPI above 1.0 means the project is ahead of schedule, not behind schedule.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The project is on schedule and on budget

    Why it's wrong here

    CPI of 0.8 shows cost overrun and SPI of 1.2 shows schedule gain, so the project is neither on budget nor on schedule. It is tempting because indices near 1.0 suggest stability, and this conclusion would hold only if both CPI and SPI equalled 1.0.

  • ✓

    The project is ahead of schedule

    Why this is correct

    An SPI of 1.2 exceeds 1.0, meaning earned value outpaces planned value, so the project is ahead of schedule. This satisfies the schedule constraint directly, independent of the CPI of 0.8, which indicates cost overrun. SPI measures schedule efficiency only, so the ahead-of-schedule conclusion holds.

  • ✗

    The project is under budget

    Why it's wrong here

    A CPI of 0.8 means each unit of work costs more than planned, so the project is over budget. It is tempting because SPI of 1.2 indicates good schedule performance, and under budget would be correct only if CPI exceeded 1.0.

  • ✗

    The project is behind schedule

    Why it's wrong here

    An SPI of 1.2 exceeds 1.0, meaning the project is ahead of schedule, not behind. It is tempting because a CPI of 0.8 signals poor cost performance, and teams often assume both indices move together; behind schedule would be correct if SPI were below 1.0.

  • ✓

    The project is over budget

    Why this is correct

    A CPI of 0.8 means every £1 spent delivers only £0.80 of earned value, so the project is over budget — the cost-efficiency constraint in the stem is breached. This conclusion follows directly from CPI falling below 1.0, independent of the healthy SPI of 1.2.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.