During a project, the project manager calculates the following: Earned Value (EV) = $50,000, Planned Value (PV) = $60,000, Actual Cost (AC) = $55,000. Which statement accurately describes the project's performance?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The project is behind schedule and over budget.

Schedule Variance (SV) = EV - PV = $50,000 - $60,000 = -$10,000, indicating behind schedule. Cost Variance (CV) = EV - AC = $50,000 - $55,000 = -$5,000, indicating over budget.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    The project is behind schedule and over budget.

    Why this is correct

    EV of $50,000 against PV of $60,000 gives a negative schedule variance, so work lags the plan; EV against AC of $55,000 gives a negative cost variance, meaning spend exceeds earned value. Both indices fall below 1.0, confirming behind schedule and over budget.

  • ✗

    The project is ahead of schedule and under budget.

    Why it's wrong here

    EV of $50,000 against PV of $60,000 gives SV of -$10,000, so the project is behind schedule, not ahead; AC of $55,000 against EV gives CV of -$5,000, so it is over budget, not under. Ahead-and-under would require EV above PV and AC below EV.

  • ✗

    The project is ahead of schedule and over budget.

    Why it's wrong here

    The cost half is right: AC $55,000 above EV $50,000 gives CV of -$5,000, so over budget. The schedule half is wrong: EV $50,000 below PV $60,000 gives SV of -$10,000, so behind schedule. Ahead requires EV above PV.

  • ✗

    The project is behind schedule and under budget.

    Why it's wrong here

    The schedule half is right: EV $50,000 below PV $60,000 means behind schedule. The cost half is wrong: AC $55,000 exceeds EV $50,000, giving CV of -$5,000, so the project is over budget. Under budget requires AC below EV.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.