PK0-005 Project Life Cycle Practice Question
A project manager is performing quantitative risk analysis. Which THREE of the following techniques are commonly used? (Select three.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Monte Carlo simulation
Quantitative risk analysis techniques include expected monetary value (EMV), sensitivity analysis, and Monte Carlo simulation. Probability/impact matrix is qualitative, and SWOT analysis is a qualitative technique.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
SWOT analysis
Why it's wrong here
SWOT analysis is a qualitative technique.
- ✓
Monte Carlo simulation
Why this is correct
Monte Carlo simulation is quantitative.
- ✓
Sensitivity analysis
Why this is correct
Sensitivity analysis is quantitative.
- ✓
Expected monetary value (EMV)
Why this is correct
EMV is a quantitative technique.
- ✗
Probability and impact matrix
Why it's wrong here
This is a qualitative technique.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.