PK0-005 Project Life Cycle Practice Question
A project has an Earned Value (EV) of $50,000, Actual Cost (AC) of $60,000, and Planned Value (PV) of $55,000. What is the Cost Performance Index (CPI), and what does it indicate?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
0.83; over budget
CPI = EV/AC = 50,000/60,000 = 0.83. A CPI less than 1 indicates the project is over budget.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
0.83; over budget
Why this is correct
Correct: CPI = 0.83, less than 1 means over budget.
- ✗
1.20; under budget
Why it's wrong here
Incorrect calculation.
- ✗
0.83; on budget
Why it's wrong here
CPI of 0.83 is not on budget; it is over budget.
- ✗
0.91; under budget
Why it's wrong here
Incorrect calculation.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.