- A
Issue log
Why wrong: Issue log records problems that have occurred, not potential risks.
- B
Risk register
The risk register tracks identified risks and their status after changes.
- C
Lessons learned
Why wrong: Lessons learned are captured after project phases or completion.
- D
Stakeholder register
Why wrong: Stakeholder register lists stakeholders, not risks.
Quick Answer
The answer is the risk register. When a change request is approved and the project baseline is updated, the risk register must also be updated because any approved change can introduce new risks, alter the probability or impact of existing risks, or make some risks obsolete. The risk register is the formal document that captures identified risks, their analysis, and response plans, so a baseline change directly affects the project’s risk profile. On the CompTIA Project+ PK0-005 exam, this tests your understanding that change control and risk management are tightly linked—a common trap is to update only the schedule or budget baseline while forgetting the risk register. To remember, think of the “Change-Risk Chain”: every approved change triggers a risk review. A simple memory tip is “No baseline update without a risk register update.”
PK0-005 Tools and Documentation Practice Question
This PK0-005 practice question tests your understanding of tools and documentation. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
After a change request is approved, the project manager updates the project baseline. Which document must also be updated to reflect the impact of the change on project risks?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Risk register
When a change request is approved and the project baseline is updated, the risk register must also be updated because the change may introduce new risks, alter the probability or impact of existing risks, or render some risks obsolete. The risk register is the formal document that captures identified risks, their analysis, and response plans, so any baseline change directly affects the risk profile of the project.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Issue log
Why it's wrong here
Issue log records problems that have occurred, not potential risks.
- ✓
Risk register
Why this is correct
The risk register tracks identified risks and their status after changes.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Lessons learned
Why it's wrong here
Lessons learned are captured after project phases or completion.
- ✗
Stakeholder register
Why it's wrong here
Stakeholder register lists stakeholders, not risks.
Common exam traps
Common exam trap: answer the scenario, not the keyword
CompTIA often tests the distinction between reactive documents (issue log) and proactive documents (risk register), so the trap here is confusing a change's potential future risks with current issues that have already materialized.
Detailed technical explanation
How to think about this question
The risk register is a living document that includes fields such as risk ID, description, probability, impact score, risk owner, and response strategy. When a change request is approved, the project manager should perform a risk reassessment to update these fields, ensuring the risk register reflects the current state of the project. In real-world scenarios, a scope change might increase technical complexity, raising the probability of integration failures, which must be documented in the risk register to trigger appropriate mitigation actions.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Tools and Documentation — study guide chapter
Learn the concepts, then practise the questions
- →
Tools and Documentation practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Tools and Documentation — This question tests Tools and Documentation — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Risk register — When a change request is approved and the project baseline is updated, the risk register must also be updated because the change may introduce new risks, alter the probability or impact of existing risks, or render some risks obsolete. The risk register is the formal document that captures identified risks, their analysis, and response plans, so any baseline change directly affects the risk profile of the project.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 30, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.