Define activities, Sequence activities, Estimate activity resources, Estimate activity durations, Develop schedule

Schedule development follows: define activities, sequence, estimate resources, estimate durations, then develop the schedule.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Define activities, Sequence activities, Estimate activity resources, Estimate activity durations, Develop schedule

    Why this is correct

    This is the correct order because it follows the logical progression: first identify what needs to be done, then determine the order, then figure out the resources and time required, and finally create the schedule.

  • ✗

    Define activities, Estimate activity resources, Estimate activity durations, Sequence activities, Develop schedule

    Why it's wrong here

    This is incorrect because sequencing should occur before estimating resources and durations; without knowing the order, resource and duration estimates may be inaccurate.

  • ✗

    Sequence activities, Define activities, Estimate activity resources, Estimate activity durations, Develop schedule

    Why it's wrong here

    This is incorrect because activities must be defined before they can be sequenced; you cannot sequence undefined activities.

  • ✗

    Define activities, Sequence activities, Estimate activity durations, Estimate activity resources, Develop schedule

    Why it's wrong here

    This is incorrect because estimating resources typically comes before estimating durations; the type and availability of resources affect how long activities take.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.