PK0-005 Practice Question: Basics of IT Infrastructure and IT Project Management
Order the steps for creating a project schedule.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Define activities, Sequence activities, Estimate activity resources, Estimate activity durations, Develop schedule
Schedule development follows: define activities, sequence, estimate resources, estimate durations, then develop the schedule.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Define activities, Sequence activities, Estimate activity resources, Estimate activity durations, Develop schedule
Why this is correct
This is the correct order because it follows the logical progression: first identify what needs to be done, then determine the order, then figure out the resources and time required, and finally create the schedule.
- ✗
Define activities, Estimate activity resources, Estimate activity durations, Sequence activities, Develop schedule
Why it's wrong here
This is incorrect because sequencing should occur before estimating resources and durations; without knowing the order, resource and duration estimates may be inaccurate.
- ✗
Sequence activities, Define activities, Estimate activity resources, Estimate activity durations, Develop schedule
Why it's wrong here
This is incorrect because activities must be defined before they can be sequenced; you cannot sequence undefined activities.
- ✗
Define activities, Sequence activities, Estimate activity durations, Estimate activity resources, Develop schedule
Why it's wrong here
This is incorrect because estimating resources typically comes before estimating durations; the type and availability of resources affect how long activities take.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 11, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.