A project manager is monitoring project performance. Which TWO earned value metrics are used to assess cost efficiency?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Cost Variance (CV)

Cost Performance Index (CPI) and Cost Variance (CV) are metrics that measure cost efficiency. CPI = EV/AC, CV = EV - AC.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Estimate at Completion (EAC)

    Why it's wrong here

    EAC is a forecast, not a measure of efficiency.

  • Schedule Variance (SV)

    Why it's wrong here

    SV measures schedule performance.

  • Cost Variance (CV)

    Why this is correct

    CV is the difference between earned value and actual cost.

  • Schedule Performance Index (SPI)

    Why it's wrong here

    SPI measures schedule efficiency, not cost.

  • Cost Performance Index (CPI)

    Why this is correct

    CPI indicates cost efficiency; >1 is under budget, <1 is over budget.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.