Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: In a construction project, the foundation must be…

In a construction project, the foundation must be completed before the framing can begin. This is an example of which type of dependency?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Mandatory dependency

Mandatory dependencies, also known as hard logic, are inherent in the nature of the work and cannot be changed.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Resource constraint

    Why it's wrong here

    A resource constraint is a limitation on availability of resources, not a dependency.

  • External dependency

    Why it's wrong here

    External dependencies involve factors outside the project, such as vendor deliveries.

  • Mandatory dependency

    Why this is correct

    Foundation before framing is a physical necessity, making it a mandatory dependency.

  • Discretionary dependency

    Why it's wrong here

    Discretionary dependencies are based on best practices, not physical necessity.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.