PK0-005 Practice Question: In a construction project, the foundation must be…
In a construction project, the foundation must be completed before the framing can begin. This is an example of which type of dependency?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Mandatory dependency
Mandatory dependencies, also known as hard logic, are inherent in the nature of the work and cannot be changed.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Resource constraint
Why it's wrong here
A resource constraint is a limitation on availability of resources, not a dependency.
- ✗
External dependency
Why it's wrong here
External dependencies involve factors outside the project, such as vendor deliveries.
- ✓
Mandatory dependency
Why this is correct
Foundation before framing is a physical necessity, making it a mandatory dependency.
- ✗
Discretionary dependency
Why it's wrong here
Discretionary dependencies are based on best practices, not physical necessity.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.