Which document formally authorizes a project and provides the project manager with the authority to apply organizational resources?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project charter

The project charter authorizes the project and assigns the project manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project management plan

    Why it's wrong here

    The plan is developed after authorization.

  • Project charter

    Why this is correct

    The charter formally authorizes the project.

  • Project scope statement

    Why it's wrong here

    The scope statement defines the scope but does not authorize the project.

  • Work breakdown structure

    Why it's wrong here

    WBS decomposes deliverables; it does not authorize.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.