mediumMultiple ChoiceObjective-mapped
PK0-005 Managing a marketing campaign project Practice Question
You are managing a marketing campaign project. The team uses a project management software that includes a resource management module. You notice that several team members are overallocated, and project tasks are at risk of delay. The software allows you to view resource capacity and assignments, but the data is not being updated regularly. You need to ensure resource conflicts are identified and resolved quickly. Which action should you take?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Establish a weekly review of resource utilization and hold team leads accountable for updates
Establishing a recurring review of resource utilization ensures ongoing monitoring and early conflict detection, and holding team leads accountable ensures data is updated regularly. Option A is wrong because reassigning tasks without analysis may cause further imbalance. Option B is wrong because automatic leveling might not consider project priorities or dependencies. Option D is wrong because focusing only on critical path tasks ignores resource conflicts on non-critical tasks, which can still delay the project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Reassign tasks from overallocated resources to under allocated ones immediately
Why it's wrong here
May not consider skill requirements or task dependencies.
- ✗
Enable the software's automatic resource leveling feature
Why it's wrong here
Automatic leveling may delay tasks without considering priorities.
- ✓
Establish a weekly review of resource utilization and hold team leads accountable for updates
Why this is correct
Regular reviews ensure conflicts are identified and resolved proactively.
- ✗
Only monitor the critical path tasks for resource conflicts
Why it's wrong here
Non-critical tasks can also cause delays.
Visual reference
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.