Courseiva
Project Life Cycle →mediumMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project manager is estimating the cost of a new software development project. She uses the actual cost of a similar past project and adjusts for differences in size and complexity. Which estimation technique is she using?

⚠ Common exam trap

PK0-005 often tests the confusion between analogous and parametric estimation — candidates see 'historical data' and jump to parametric, but parametric requires a measurable unit rate applied to a variable, whereas analogous uses whole-project comparison.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Analogous estimation

Analogous estimation uses historical data from a similar past project as the basis for estimating the current project, adjusting for known differences in size, complexity, or scope. The scenario explicitly describes using actual cost of a similar past project with adjustments, which is the textbook definition of analogous (top-down) estimating. It is fast and inexpensive but less accurate than bottom-up or parametric methods.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Three-point estimation

    Why it's wrong here

    Three-point estimation uses optimistic, pessimistic, and most likely cost values to calculate a weighted average, but the scenario describes a single historical baseline adjusted for size and complexity—this is analogous (parametric or analogous estimation), not a probabilistic range. It is tempting because three-point estimation is a common technique for refining cost accuracy, and it would be correct if the project manager had gathered three separate estimates from subject-matter experts to account for uncertainty rather than relying on one past project.

  • ✗

    Parametric estimation

    Why it's wrong here

    Parametric estimation applies a statistical rate per unit, such as cost per function point, to a project variable. It is tempting because it also uses historical data, but it would be correct when a measurable unit rate exists and can be multiplied by the project's size.

  • ✗

    Bottom-up estimation

    Why it's wrong here

    Bottom-up estimation sums individual work-package or task estimates to reach a total. It is tempting because it is highly accurate, but it would be correct when detailed task-level data is available, not when scaling a single analogous project's actual cost.

  • ✓

    Analogous estimation

    Why this is correct

    Analogous estimation derives duration or cost from the actual figures of a comparable historical project, then scales them for size and complexity differences. Here the manager uses a similar past project's real cost, adjusted for scope variance, satisfying the stem's requirement for a top-down, experience-based estimate rather than bottom-up or parametric calculation.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.