Which of the following is the primary purpose of a feasibility study during the initiating phase?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To determine if the project is viable

A feasibility study assesses whether the project is viable and worth doing.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To develop a communication plan

    Why it's wrong here

    Communication planning is part of planning.

  • To identify all project risks

    Why it's wrong here

    Risk identification is part of planning.

  • To create a detailed project schedule

    Why it's wrong here

    Scheduling is done in planning.

  • To determine if the project is viable

    Why this is correct

    Feasibility study evaluates viability.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.