Courseiva
mediumMultiple Choice

PK0-005 Practice Question: A project sponsor asks for a report showing the…

A project sponsor asks for a report showing the planned vs. actual cost performance. Which project document contains the necessary data to create this report?

⚠ Common exam trap

The PK0-005 exam often tests the distinction between the WBS (scope decomposition) and the cost baseline (budget allocation), leading candidates to mistakenly select the WBS because it is a familiar document, even though it lacks the cost data needed for the report.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Cost baseline

The cost baseline is the approved version of the project budget, including contingency reserves, against which actual cost performance is measured. It provides the planned cost data (budgeted cost of work scheduled) and, when combined with actual cost data from the project's accounting system, enables the calculation of cost variance and cost performance index for the report. The sponsor's request for planned vs. actual cost performance directly requires the cost baseline as the reference document.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Stakeholder engagement plan

    Why it's wrong here

    The stakeholder engagement plan records how stakeholders are engaged and managed, not financial figures, so it holds no planned or actual cost data. It is tempting because engagement activities can consume budget, but that plan would be the right source only when determining stakeholder communication needs and involvement levels.

  • ✗

    Requirements traceability matrix

    Why it's wrong here

    The requirements traceability matrix links requirements to their origin, status and test coverage; it tracks scope, not expenditure, so it cannot supply planned versus actual cost figures. It would be the correct document when verifying that each requirement maps to a deliverable and has been tested.

  • ✓

    Cost baseline

    Why this is correct

    The cost baseline is the time-phased budget that the sponsor approved, so it supplies planned cost per period. Actual costs come from project accounting records, and comparing the two yields cost variance and the CPI. It therefore satisfies the stem's requirement for planned versus actual cost performance data.

  • ✗

    Work breakdown structure

    Why it's wrong here

    The work breakdown structure decomposes deliverables into work packages but carries no monetary values, so it cannot show planned versus actual cost. It is tempting because cost estimates are built from its work packages; it would be correct when defining scope hierarchy or providing the basis for estimating.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.