Which THREE documents are typically part of the project management plan?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Risk management plan
The scope management plan, risk management plan, and communication plan are subsidiary plans. The project charter authorizes the project and is separate; the lessons learned register is created after phases or project closure.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Risk management plan
Why this is correct
The risk management plan is part of the PM plan.
- ✗
Project charter
Why it's wrong here
The project charter is an input to the PM plan, not a component of it.
- ✗
Lessons learned register
Why it's wrong here
Lessons learned are documented throughout the project but are not part of the PM plan.
- ✓
Scope management plan
Why this is correct
The scope management plan is a subsidiary plan within the PM plan.
- ✓
Communication plan
Why this is correct
The communication plan is a subsidiary plan within the PM plan.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PK0-005
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which TWO documents are typically included in the project management plan?
medium- A.Work breakdown structure dictionary
- ✓ B.Scope management plan
- C.Risk register
- ✓ D.Schedule management plan
- E.Project charter
Why B: The scope management plan and schedule management plan are both subsidiary plans that form part of the project management plan. They define how the project scope and schedule will be defined, developed, monitored, controlled, and verified throughout the project lifecycle. These are required by the PMBOK Guide and are included in the project management plan documentation.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.