PK0-005 Practice Question: Which THREE documents are typically part of the…

Which THREE documents are typically part of the project management plan?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk management plan

The scope management plan, risk management plan, and communication plan are subsidiary plans. The project charter authorizes the project and is separate; the lessons learned register is created after phases or project closure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk management plan

    Why this is correct

    The risk management plan is part of the PM plan.

  • Project charter

    Why it's wrong here

    The project charter is an input to the PM plan, not a component of it.

  • Lessons learned register

    Why it's wrong here

    Lessons learned are documented throughout the project but are not part of the PM plan.

  • Scope management plan

    Why this is correct

    The scope management plan is a subsidiary plan within the PM plan.

  • Communication plan

    Why this is correct

    The communication plan is a subsidiary plan within the PM plan.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO documents are typically included in the project management plan?

medium
  • A.Work breakdown structure dictionary
  • B.Scope management plan
  • C.Risk register
  • D.Schedule management plan
  • E.Project charter

Why B: The scope management plan and schedule management plan are both subsidiary plans that form part of the project management plan. They define how the project scope and schedule will be defined, developed, monitored, controlled, and verified throughout the project lifecycle. These are required by the PMBOK Guide and are included in the project management plan documentation.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.