PK0-005 · domain
Project Management Concepts
This domain covers the foundational vocabulary and judgment calls of PK0-005: project vs. operations, stakeholder roles, organizational structures, and methodology selection. Questions are scenario-based, asking you to identify responsibilities, compare business cases using NPV, or match Agile, Waterfall, or hybrid approaches to described team behaviors.
Focused practice
Practice Project Management Concepts questions
Scored sessions drawing only from this domain — pick a length below.
Start 20-question practice test →What this domain covers
What to know about Project Management Concepts
You must map stakeholder roles to their correct responsibilities, pick projects using financial metrics like NPV, and classify methodologies from scenario clues. The single most important thing: know that the sponsor authorizes and funds, while the project manager plans and executes.
Sponsor versus project manager versus PMO responsibilities and authority levels
Project selection using NPV, ROI, payback period, and cost-benefit analysis
Predictive, Agile, and hybrid methodology selection based on requirements stability
Organizational structures: functional, matrix, and projectized and their reporting lines
Watch out for
Common Project Management Concepts exam traps
- ▸Confusing the sponsor's funding and escalation role with the project manager's day-to-day execution duties.
- ▸Choosing a project with a negative NPV because it has a lower initial cost or shorter timeline.
- ▸Labeling any team with meetings as Agile, ignoring time-boxed iterations and evolving requirements.
Question index
All Project Management Concepts questions (163)
Click any question to see the full explanation, or start a practice session above.
A project manager is closing out a project that delivered a new customer portal. The sponsor wants to ensure that lessons from this effort improve future projects and that the product is properly handed over. Which TWO activities should the project manager perform as part of closing the project? (Choose two.)
Medium2Which THREE of the following are responsibilities of a project manager? (Select THREE).
Hard3During project execution, a key stakeholder requests additional features that were not originally approved. The project manager is concerned about scope creep. Which type of project constraint is most directly impacted by scope creep?
Hard4A project manager has just received formal approval to proceed with a new payroll system project. The sponsor asked for a document that formally names the project manager and gives authority to apply organizational resources to project activities. Which document should the project manager reference?
Easy5A project manager is leading a team to develop a new mobile application. The project has a fixed budget and a strict deadline. During the execution phase, the stakeholder requests additional features that were not originally planned. Which project constraint is most directly affected by this request?
Easy6In which type of organizational structure does the project manager have the least authority?
Medium7A project manager is working in a matrix organization. The project team members report to both the project manager and their functional managers. The project manager has moderate authority and shares resources. This type of matrix is known as:
Medium8A project team is developing a new mobile application. During execution, a stakeholder requests additional features that were not in the original scope. The project manager is concerned about scope creep. Which TWO actions should the project manager take to manage this request? (Select TWO).
Easy9A project manager is selecting a project from several proposals. The project with the highest Net Present Value (NPV) also has the longest payback period. Which TWO factors should the project manager consider when recommending this project? (Select TWO).
Medium10A project manager is evaluating two project proposals. Project A has an initial investment of $100,000 and is expected to generate cash flows of $30,000 per year for 5 years. Project B has an initial investment of $50,000 and cash flows of $20,000 per year for 3 years. Using payback period, which project should be selected?
Hard11A project team is using an agile methodology to develop a new feature. The product owner frequently reprioritizes the backlog based on changing customer needs. Which characteristic of agile does this BEST illustrate?
Medium12A newly assigned project manager is reviewing the document that formally authorizes the existence of a project and grants the project manager authority to apply organizational resources to project activities. Which document is the project manager reviewing?
Easy13During a project, a stakeholder requests additional features that were not in the original scope. The project manager adds these features without formal change control. This is an example of:
Hard14A company wants to select a project based on the time it takes to recover the initial investment. Which project selection method should be used?
Easy15A senior manager is comparing two projects for selection. The manager wants to use a method that considers the time value of money. Which TWO project selection methods incorporate the time value of money?
Medium16A project manager is leading a software development project with stable requirements and a fixed budget. The team prefers a sequential approach with clear phases. Which methodology is most appropriate?
Medium17An organization has multiple projects that are not directly related but are all aimed at achieving the company's strategic goal of expanding into new markets. Which term best describes this collection?
Medium18A project manager has been asked to lead a project that will replace a legacy payroll system. The vendor contract requires a firm completion date tied to a regulatory deadline, and the budget was approved at a fixed ceiling. During the first planning workshop, the sponsor asks the project manager to add a self-service reporting portal that was not part of the approved business case. What should the project manager do FIRST?
Medium19Who is typically responsible for providing the project budget and resources, and for resolving issues that are beyond the project manager's authority?
Medium20A project has a budget of $100,000 and a duration of 12 months. After 6 months, the project is 50% complete and has spent $60,000. What is the cost variance?
Medium21An organization is evaluating two potential projects. Project A has an NPV of $50,000 and a payback period of 2 years. Project B has an NPV of $40,000 and a payback period of 1.5 years. The organization's policy is to select projects with the highest NPV. Which project should be selected?
Medium22A project manager is preparing a stakeholder engagement assessment for a hospital records migration. The sponsor has been supportive but has recently become distracted by another initiative, and the radiology department head actively opposes the new workflow. The project manager wants to move each stakeholder toward the engagement level needed for success. Which TWO actions are MOST appropriate? (Choose two.)
Medium23A project manager is leading a software localization project with team members in three time zones. The PM notices that decisions made in the weekly status call are frequently reversed by absent team members after the call, and the schedule baseline has slipped twice. Which action should the PM take to improve decision-making and reduce rework?
Hard24During project execution, the project manager notices that the team is adding extra features that were not requested by the customer. This is an example of which common project constraint issue?
Medium25A project manager has been assigned to deliver a new customer portal. The sponsor wants to know who holds ultimate accountability for the project's success and who can approve changes to the approved budget baseline. Which role should the project manager identify?
Easy26Which of the following is NOT a phase in the typical project life cycle?
Easy27A project manager is leading a cross-functional team in a matrix organization. The project is experiencing conflicts between team members due to competing priorities from their functional departments. Which THREE techniques should the project manager use to resolve resource conflicts? (Select THREE).
Medium28A project manager is closing a project that delivered a new customer relationship management system. Which THREE activities are part of the closing process? (Select THREE).
Hard29A project manager is building the team for a data-migration project. The sponsor wants to know how the PM will acquire personnel, how team members will be trained and managed, how performance will be appraised, and how the team will eventually be released. In which project management plan component should the PM document these items?
Medium30A steering committee is reviewing project performance. Which of the following is a key responsibility of the steering committee?
Hard31Which TWO of the following are characteristics of a project? (Select TWO).
Medium32A project manager is preparing a stakeholder engagement approach for a project that will affect several departments. One department head has high influence over funding decisions but currently shows little interest in the project and has not responded to meeting invitations. According to a power/interest classification, how should the project manager treat this stakeholder?
Hard33A project manager is leading a project in an organization that uses a hybrid methodology. The team follows a predictive approach for requirements gathering and design, but uses iterative sprints for development. Which life cycle best describes this project?
Hard34A project team is adding extra features to a deliverable that were not requested by the customer, in an effort to improve the product. This practice is known as:
Easy35A project manager is building the team for a regulatory compliance project with a fixed external deadline. The organization uses a strong matrix structure. The project manager needs to secure a senior security architect who is also in high demand on other initiatives. Which action is MOST likely to obtain this resource commitment?
Medium36A software development team uses short, time-boxed iterations, daily stand-up meetings, and a prioritized backlog. Requirements are expected to evolve throughout the project. Which project management methodology is being used?
Medium37During project selection, an organization evaluates multiple projects using financial methods. Which THREE of the following are commonly used financial project selection methods? (Select THREE).
Hard38Which TWO of the following are primary responsibilities of the project manager? (Select two.)
Medium39During project execution, a stakeholder requests additional features that were not in the original scope. The project manager identifies this as scope creep. What is the best action for the project manager to take?
Medium40A project manager is assigned to a project with a fixed deadline, a fixed budget, and a scope that cannot be reduced. During planning, the team discovers that meeting all three constraints simultaneously is not feasible with current resources. What is the MOST appropriate action for the project manager to take?
Medium41A project manager is leading an infrastructure modernization effort that will take 14 months. The organization has a limited capital budget, but the project sponsor has secured approval to deliver a small, working subset of the highest-priority network upgrades within the first four months. The remaining upgrades will be delivered in later releases based on available funding. Which project life cycle best fits this approach?
Medium42A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. What does this indicate?
Hard43Which TWO of the following are examples of project constraints? (Select TWO).
Medium44A project manager is preparing the team charter for a newly formed project team that includes members from three departments and two external partners. The organization has a history of unresolved interpersonal friction on cross-departmental efforts. Which action BEST reflects the purpose of a team charter in this situation?
Easy45Who is responsible for providing the project with resources and removing obstacles that are beyond the project manager's control?
Easy46A project manager is developing the project charter for a new payroll system. The sponsor asks which document will formally authorize the project and give the project manager authority to apply organizational resources. Which document should the project manager reference?
Easy47A project manager is reviewing the project charter for a new data migration project. The charter authorizes the project and names the project manager, but the project manager notices that the success criteria and high-level budget are vague. The sponsor is eager to start work immediately. What should the project manager do before proceeding with detailed planning?
Medium48A project manager is leading a software development project in a matrix organization. The project manager shares resources with functional managers. In this type of organizational structure, which of the following BEST describes the project manager's authority?
Medium49A project manager has been authorized to lead a new customer-portal replacement effort. Before any detailed scheduling begins, the PM needs to formally document the measurable outcomes the portal must achieve, the boundaries of what will and will not be delivered, and the acceptance criteria the customer will use. Which document should the project manager produce FIRST to capture these items?
Easy50A project manager is two weeks into a six-week infrastructure upgrade when the data center landlord announces mandatory electrical maintenance that will shut down power to the racks for 48 hours during week four. The PM has float of only three days on the critical path. Which document should the PM update to record this external constraint and its potential effect on the schedule?
Medium51An organization is launching a project to design a brand-new autonomous delivery vehicle. The technology is unproven, requirements will emerge through prototyping, and the customer expects frequent demonstrations. Which approach should the project manager recommend?
Medium52A company is initiating a project to develop a new mobile application. The project manager needs to secure approval and funding. Which project role is primarily responsible for providing the necessary resources and championing the project?
Easy53In which project life cycle phase are project risks identified and a risk management plan created?
Medium54A project manager is reviewing the project constraints. The triple constraint traditionally includes scope, time, and cost. However, quality is also often considered a constraint. Which TWO of the following are part of the triple constraint? (Select TWO).
Medium55A project manager is leading a project that uses a hybrid methodology. The project has a fixed deadline but the requirements are expected to evolve. Which approach best describes how the PM should handle the project?
Hard56A project manager is using a predictive approach for a regulatory compliance project. Midway through execution, a newly published regulation invalidates a design assumption documented in the project management plan. The project manager wants to handle this in a way that preserves traceability and keeps the baseline accurate. What should the project manager do FIRST?
Hard57Which TWO of the following are key characteristics of a project? (Select TWO).
Medium58An organization is preparing to launch a project that will replace its aging payroll system. Executive leadership has assigned a sponsor, and the sponsor has asked the project manager to produce the document that formally authorizes the project and gives the project manager authority to apply organizational resources to project activities. Which document should the project manager produce?
Easy59A project manager is midway through a data center migration when the sponsor announces that the organization will divest the business unit that owns the legacy systems being migrated. The divestiture removes the business need for half of the migration scope and shifts the completion deadline forward by two months. The sponsor asks the project manager to recommend the appropriate course of action. What should the project manager do FIRST?
Hard60A project manager is leading a project with a tight budget. The team has completed all required features, but there is some remaining budget. The sponsor suggests adding a few extra features. What are TWO potential issues the project manager should consider before approving? (Choose TWO.)
Hard61A project manager is assigned to a new initiative in a matrix organization with a weak matrix structure. The project manager needs to obtain resources from functional departments. The functional managers have authority over their team members' assignments and priorities. What is the most likely challenge the project manager will face in this environment?
Hard62A project manager is reviewing the project selection methods for a new initiative. Which TWO of the following are financial project selection methods? (Choose two.)
Medium63A project manager is reviewing the project management plan before a phase gate review. The sponsor wants evidence that the plan addresses how changes will be controlled and how the project will be kept aligned with the approved baseline. Which TWO components should the project manager confirm are included? (Choose two.)
Hard64A project manager is leading a software localization project spanning three countries. The schedule baseline was approved with a duration of nine months, but the vendor delivering translated content has just reported a four-week delay caused by a shortage of certified linguists. The project manager has no authority to approve additional funds and must decide how to proceed. Which of the following actions is the MOST appropriate first step?
Medium65A project manager is leading a distributed team across three time zones. The project has a fixed deadline and high uncertainty in requirements. The sponsor wants frequent demonstrations of working product. Which project life cycle is MOST appropriate?
Hard66A project manager is selecting a project using financial methods. Which THREE of the following are valid project selection methods? (Select THREE).
Hard67A project manager is preparing the stakeholder engagement approach for a hospital construction project. The regulatory authority has high interest and high influence, and can halt the project if permits are delayed. The project manager needs to keep this stakeholder satisfied. Which classification and engagement level is MOST appropriate?
Medium68Which of the following is an example of gold plating?
Medium69A project manager is managing a project in a functional organization. Due to resource constraints, the functional manager often reassigns team members to other tasks. What is the MOST significant challenge the project manager will face?
Hard70A project to develop a mobile app is in the executing phase. The project manager uses a Kanban board to track tasks. The team is self-organizing and works in short iterations. The customer is actively involved and provides feedback frequently. Which THREE statements are true about this project?
Hard71A project manager learns that a key supplier will be three weeks late delivering a hardware component, which threatens the critical path. The PM has already asked the supplier to expedite at additional cost and has examined whether the component can be substituted. Which process is the project manager performing?
Medium72A project manager is assigned to a new software development project. The requirements are well understood and unlikely to change. Which project management methodology is most appropriate for this project?
Medium73A project manager learns that a key supplier will deliver a critical component three weeks late because of a raw material shortage at the supplier's factory. The project manager immediately notifies the sponsor, contacts two alternate vendors for quotes, and begins revising the schedule to reflect a possible slip. Which risk response strategy is the project manager applying?
Medium74A project manager is assigned to a new project with unclear requirements and expects frequent changes. Which project management methodology is most suitable?
Easy75A project manager is defining the project life cycle for a construction project where requirements are well-defined and unlikely to change. Which project management methodology is most appropriate for this scenario?
Easy76Which of the following is a key responsibility of the project sponsor?
Easy77Which project life cycle phase involves formally accepting the project deliverables and releasing resources?
Easy78A project manager is using a hybrid methodology. The project has a fixed overall budget and a high-level schedule, but some deliverables are developed iteratively with stakeholder feedback. The team works in two-week sprints for software development, while hardware procurement follows a sequential plan. Which project life cycle is being used?
Hard79A company is undertaking a one-time initiative to develop a new mobile application with a defined budget, schedule, and scope. Which term best describes this initiative?
Easy80A project to build a new office is in the planning phase. The project manager wants to use a methodology that allows for flexibility in design while still having a clear upfront plan for the overall construction. Which approach is BEST?
Medium81A project has been completed, and the project manager is conducting a lessons learned session and archiving project documents. Which project life cycle phase is being performed?
Easy82Which of the following best describes a project?
Easy83A project manager is leading a team in an organization where team members are assigned to multiple projects and report to both a functional manager and the project manager. The project manager has moderate authority over the team. Which organizational structure does this describe?
Medium84A project manager is building the team for a six-month software development project. The organization uses a functional structure, and the project manager has been told that team members will report to their functional managers for performance reviews and day-to-day priorities. The project manager needs to understand what authority is realistically available. Which type of organizational structure is described, and what is its typical impact on the project manager's authority?
Easy85Which of the following is NOT a typical constraint in the triple constraint of project management?
Easy86A project manager is chartered to deliver a new payroll system in eight months with a fixed budget of $600,000. In month three, the vendor informs the PM that a mandatory regulatory change will add 15% to the cost and two months to the schedule, but the scope is non-negotiable by law. The sponsor asks the PM to present the revised baseline for approval. Which action should the PM take FIRST?
Easy87A project manager is leading a global marketing campaign with team members in three countries and stakeholders who speak different languages. The project manager has created a detailed communication plan but is now receiving complaints that some stakeholders feel uninformed about major decisions. The project manager reviews the plan and notices that it specifies frequency and channels but does not address cultural differences or stakeholder influence levels. Which action should the project manager take to improve communication effectiveness?
Hard88A project sponsor is responsible for providing resources and championing the project. Which of the following is also a primary responsibility of the project sponsor?
Hard89A project is experiencing scope creep. Which TWO of the following are effective ways to manage scope creep? (Choose two.)
Medium90Which project life cycle phase involves obtaining formal acceptance of the project deliverables?
Medium91A project manager is planning a construction project and identifies that the project has a fixed budget and a strict deadline. The sponsor emphasizes that quality cannot be compromised. Which THREE constraints are directly affected when a change request is approved? (Select THREE).
Medium92A project is defined as a temporary endeavor undertaken to create a unique product, service, or result. Which of the following BEST describes a key characteristic of a project?
Easy93A project manager is closing out a data-center migration. During the final review, the team discovers that two servers were decommissioned without the required security wipe, which is a compliance violation. The project manager documents the issue and assigns an owner and due date. Which process is the project manager performing?
Hard94A project sponsor is a key stakeholder. Which of the following is a primary responsibility of the project sponsor?
Medium95In a matrix organization, a project manager needs to acquire a team member from a functional department. The functional manager is reluctant to release the resource due to other work. What is the best way for the project manager to address this?
Hard96A project manager is closing a project that was terminated early by the sponsor due to a strategic shift. The team has completed some deliverables, and the customer has paid for work performed. Which activity is MOST important for the project manager to perform during closure?
Medium97A project manager is leading a project with a fixed-price contract and a hard regulatory deadline. The customer has requested a new feature that would require additional testing and a two-week delay. The project manager must decide how to respond. Which action should the project manager take FIRST?
Medium98A project manager is preparing the resource management plan for a project that requires a scarce cybersecurity specialist for only three weeks of a nine-month schedule. The functional manager has warned that the specialist may be pulled onto a higher-priority incident at any time. Which action should the PM take to protect the schedule?
Hard99A project manager is planning a project in a weak matrix organization. The project manager has limited authority over team members who report to functional managers. Which TWO actions should the project manager take to improve the ability to influence project outcomes? (Choose two.)
Hard100A project manager is closing out a completed infrastructure upgrade project. The PM must ensure the project is closed in an orderly way and that lessons from the effort are preserved for future work. Which TWO activities belong to the closing phase? (Choose two.)
Hard101A project manager is selecting a methodology for a project with well-understood requirements and low expected change. Which methodology is MOST appropriate?
Medium102A project to build a website is expected to take 6 months with a fixed budget. During planning, the team determines that the requirements are well-understood and unlikely to change. Which methodology is most appropriate?
Medium103A project manager is evaluating two potential projects. Project A has an NPV of $50,000, and Project B has an NPV of -$10,000. Which project should be selected based on NPV?
Medium104Which TWO of the following are characteristics of the planning phase in the project life cycle? (Choose TWO.)
Medium105A company is considering a project with an initial investment of $100,000 and expected annual cash inflows of $30,000 for 5 years. The discount rate is 10%. What is the approximate Net Present Value (NPV)? (Present value of annuity factor for 5 years at 10% is 3.791)
Hard106A project manager is building the project team for a six-month software implementation. The organization uses a weak matrix structure. The project manager needs two developers, but the functional manager controls their day-to-day assignments and performance reviews. Which action should the project manager take FIRST to secure these resources?
Medium107Which TWO of the following are examples of gold plating? (Select two.)
Medium108A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. What does this indicate about the project's performance?
Hard109A project manager is developing the project charter for a new CRM implementation. The sponsor asks the PM to ensure the charter includes a measurable success criterion. Which of the following is the BEST example of a measurable success criterion to include in the project charter?
Medium110A project manager is assigned to a new software development project. The requirements are well understood and unlikely to change. The project team is collocated and has experience with similar projects. Which life cycle approach is MOST appropriate for this project?
Medium111A project manager is estimating effort for a data migration. The team has completed similar migrations before, so they use a weighted average of optimistic, most likely, and pessimistic estimates for each work package. Which estimating technique is the project manager applying?
Medium112A company is implementing a new HR system. The project manager wants to ensure that all requirements are gathered up front and the scope is fixed. Which project management methodology is MOST appropriate?
Medium113A project is in the planning phase and the team is determining the sequence of activities. Which project life cycle phase follows planning?
Medium114A project has a Net Present Value (NPV) of -$5,000. What does this indicate?
Medium115A project manager is analyzing the critical path of a 40-activity network diagram. Two paths converge on a milestone: one path has a total float of zero and a duration of 120 days, and the other path has a total float of three days and a duration of 118 days. A team member proposes reducing the duration of an activity on the path with three days of float by two days. What is the MOST likely effect of this change on the project?
Hard116In a matrix organization, a project manager is struggling to get resources assigned to project tasks because the functional managers prioritize operational work. Which type of matrix organization is MOST likely in place?
Medium117A project manager is assigned to a project in a matrix organization where the functional managers have significant control over team members. The PM has limited authority. This describes which type of matrix?
Hard118During project execution, the project team completes a deliverable that exceeds the specified requirements by adding extra features without authorization. This is an example of which concept?
Medium119A project manager is drafting the document that formally outlines how the project team will be structured, how often status reports will be delivered, and which tools will be used for tracking tasks. This document will be reviewed and approved before execution begins. Which document is the project manager creating?
Easy120Which project life cycle phase involves obtaining formal acceptance of the project deliverables and releasing project resources?
Medium121A project manager is closing out a data migration project. The sponsor wants assurance that all contractual requirements have been met before final payment is released to the vendor. Which activity should the project manager perform to support this assurance?
Hard122A company is evaluating two projects. Project A has an NPV of $50,000 and a payback period of 3 years. Project B has an NPV of $40,000 and a payback period of 2 years. Which project should be selected based on NPV?
Hard123A project manager is closing out a customer relationship management implementation. The sponsor asks which activities are part of the closing phase rather than the execution phase. (Choose two.)
Medium124During project execution, the project manager notices that the development team has been adding extra features that were not requested by the customer. Which of the following describes this behavior?
Medium125A project manager is working in an organization where the project team members report to both a functional manager and the project manager. The project manager has moderate authority and shares resource management with functional managers. This is an example of which organizational structure?
Medium126A project manager works in an organization where team members report to both a functional manager and a project manager. The project manager has moderate authority and shares resource control with the functional manager. Which type of organizational structure does this describe?
Medium127A project sponsor is reviewing a proposal for a new project. The expected cash flows are: Year 0: -$100,000; Year 1: $30,000; Year 2: $40,000; Year 3: $50,000. The discount rate is 10%. Which of the following is the Net Present Value (NPV) of the project?
Hard128A project sponsor is reviewing a project that has a Net Present Value (NPV) of -$15,000. What should the sponsor recommend?
Hard129A project manager is evaluating the financial viability of several proposed projects. The steering committee wants to select projects that maximize return over time. Which TWO financial metrics should the project manager use to compare long-term profitability? (Select TWO).
Medium130A project manager is finalizing the resource management plan for a project that depends heavily on a scarce database administrator skill set. The sponsor asks which activities belong to the Acquire Resources process rather than to Plan Resource Management. Which TWO activities should the project manager identify? (Choose two.)
Medium131A project manager is leading a project to implement a new enterprise resource planning (ERP) system. The project is in the executing phase. The project manager needs to ensure that the project team follows the approved processes and that the project remains on track. Which TWO of the following activities are part of the Monitoring and Controlling process group? (Choose two.)
Hard132In which organizational structure does the project manager have the least authority?
Easy133A project manager is preparing to close out a construction project. The final deliverable was accepted by the customer two weeks ago, but several team members have already been reassigned to a new initiative. The project manager still needs to obtain formal sign-off from the customer, archive project documents, and release remaining resources. Which activity should the project manager complete FIRST in the closing phase?
Medium134During project initiation, the project sponsor provides the project manager with a document that authorizes the project and assigns the project manager. This document also outlines high-level scope, budget, and timeline. Which document is this?
Hard135A project manager is midway through a data migration project when the vendor informs them that a critical API will be deprecated in six weeks, well before the planned cutover. The project manager convenes the team and identifies three candidate responses: rewrite the integration, negotiate a vendor extension, or move the cutover earlier. What has the project manager MOST directly performed?
Hard136A project manager is managing a construction project. The scope is well-defined, but the customer is open to minor changes during execution. Which methodology is most suitable?
Easy137A project manager is closing out a customer portal project when a key vendor reports that a delivered component fails security acceptance criteria. The component is already installed in the production environment, and the customer has begun using it. The project manager must decide how to handle the situation before final sign-off. Which TWO actions are MOST appropriate? (Choose two.)
Hard138In which organizational structure does the project manager have the least authority over project resources?
Easy139During project execution, a key stakeholder requests a new feature that was not in the original scope. The project manager is concerned about the impact on the schedule and budget. This is an example of:
Medium140A project is falling behind schedule. The project manager considers crashing or fast-tracking. Which THREE statements about these techniques are correct? (Select three.)
Hard141A project manager is evaluating two projects. Project A has an initial investment of $50,000 and expected annual returns of $15,000 for 5 years. Project B has an initial investment of $80,000 and expected annual returns of $22,000 for 5 years. Based on payback period, which project should be selected, and what is the payback period for that project?
Hard142A project manager is preparing the team charter for a distributed project team that spans three time zones. The sponsor wants the charter to reduce friction before work begins. Which TWO items belong in the team charter? (Choose two.)
Hard143A project manager is defining the roles and responsibilities for a project. Which TWO of the following are typical responsibilities of the project sponsor? (Select TWO).
Easy144A project manager is working on a project with a fixed-price contract. The customer requests a significant change that will increase the project scope and cost. The project manager documents the change and submits it to the change control board (CCB). Which of the following is the MOST likely outcome if the CCB approves the change?
Medium145A project manager has been assigned to lead a project that will deploy a new enterprise resource planning system across five regional offices. Executive leadership has emphasized that the go-live date cannot move because of a regulatory deadline, and the budget has been capped. During planning, the project manager realizes the team cannot deliver the full original feature set within the fixed time and budget. Which TWO actions should the project manager take to address this situation? (Choose two.)
Hard146Which of the following best describes a program?
Easy147During a project, the team adds extra features to a deliverable because they believe it will increase customer satisfaction, even though the features were not specified in the requirements. This is an example of:
Medium148A project manager is closing out a fixed-price construction project. All deliverables have been accepted, final payment has been received, and the product has been transitioned to the operations team. The project manager is now compiling the final report and archiving records. Which of the following BEST describes the purpose of this activity?
Medium149A project manager is evaluating two project proposals. Proposal A has an NPV of $50,000 and a payback period of 2 years. Proposal B has an NPV of $30,000 and a payback period of 1.5 years. Which proposal is more financially beneficial based on NPV?
Medium150A project manager is assigned to a new software development project with clearly defined requirements and minimal expected changes. Which project management methodology is most appropriate for this scenario?
Easy151Midway through a six-month project, the project manager notices that the team has completed 40 percent of the planned work but has consumed 60 percent of the budget. The sponsor asks for a forecast of the total cost at completion based on current performance. Which earned value metric should the project manager use to answer this question?
Hard152A project manager is planning a marketing campaign for a new product launch. The campaign has a tight budget and strict deadline. During execution, the marketing team proposes adding a social media component that was not in the original scope. The project manager is concerned about scope creep. Which TWO actions should the project manager take to manage this situation?
Medium153A project manager is leading a project to develop a new mobile application. The team is distributed across three time zones. The project manager needs to ensure that all team members have access to the latest project documents and can collaborate in real time. Which of the following tools is BEST suited for this purpose?
Easy154A project team is developing a new software product. The product owner frequently changes priorities based on customer feedback. The team needs to adapt quickly and deliver value incrementally. Which project management methodology is most suitable?
Medium155Which of the following best defines a project?
Easy156A collection of projects and programs managed together to achieve strategic objectives is known as a:
Easy157In which organizational structure does a project manager have the highest level of authority?
Easy158A project manager joins an initiative that will deliver a mobile banking feature. Regulatory requirements are stable and well documented, but the marketing team keeps revising the desired user experience every few weeks. The organization wants early feedback from real customers while limiting rework on the regulated components. Which approach BEST fits this project?
Medium159A project manager is evaluating two potential projects. Project A has an NPV of $50,000, while Project B has an NPV of -$10,000. Which project should the organization select based solely on NPV?
Hard160A project manager is reviewing project selection methods. Which method calculates the present value of future cash flows minus the initial investment?
Medium161A project manager is preparing a benefits realization plan for a project that will replace a legacy order-processing system. The sponsor asks how the team will confirm that the intended business value is actually achieved after the system goes live. Which action should the project manager take to address the sponsor's concern?
Medium162A project manager is assigned to a program that includes multiple projects aimed at digital transformation. Which TWO statements correctly describe the relationship between projects, programs, and portfolios? (Select TWO).
Hard163A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following statements is TRUE?
HardOther domains
All PK0-005 exam domains
Frequently asked questions
- What does the Project Management Concepts domain cover on the PK0-005 exam?
- You must map stakeholder roles to their correct responsibilities, pick projects using financial metrics like NPV, and classify methodologies from scenario clues. The single most important thing: know that the sponsor authorizes and funds, while the project manager plans and executes.
- How many questions are in this domain?
- This page lists all 163 Project Management Concepts questions in the PK0-005 question bank. The actual exam draws from this domain proportionally to its weighting in the official exam blueprint.
- What is the best way to practise this domain?
- Start with a short focused session (10 questions) to identify gaps, then work through explanations. Repeat with a longer session once the weak areas feel solid.
- Can I practise only Project Management Concepts questions?
- Yes — the session launcher on this page filters questions to this domain only. Choose any session length for inline explanations and scoring.