During a project, the team adds extra features to a deliverable because they believe it will increase customer satisfaction, even though the features were not specified in the requirements. This is an example of:

⚠ Common exam trap

PK0-005 often tests the confusion between gold plating (team-initiated extra features) and scope creep (stakeholder-driven uncontrolled scope growth) — candidates frequently swap the two.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Gold plating

Gold plating is the deliberate addition of features or functionality that were not requested in the requirements, typically done by the team believing it adds value. Because the team voluntarily added unrequested features to increase customer satisfaction, this matches the definition of gold plating exactly. It differs from scope creep, which is uncontrolled expansion of scope usually driven by stakeholders or changing requirements rather than the team's own initiative.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Gold plating

    Why this is correct

    Gold plating occurs when the team adds functionality beyond the agreed requirements, exactly as described. It satisfies the scenario's constraint of unsanctioned scope addition, consuming budget and time without customer approval. Unlike scope creep, which is stakeholder-driven, gold plating is initiated internally by the project team itself.

  • ✗

    Scope creep

    Why it's wrong here

    Adding unrequested features is gold plating, not scope creep; scope creep is uncontrolled growth in requirements, whereas here the team deliberately exceeds the agreed baseline. It is tempting because both expand work beyond the specification, but the distinguishing mechanism is unauthorised requirement change versus voluntary over-delivery.

  • ✗

    Risk response

    Why it's wrong here

    Risk response addresses identified threats through avoidance, transfer, mitigation or acceptance; adding unrequested features is not a response to any logged risk. It is tempting because both involve deliberate action, but risk response requires a prior risk register entry, which this scenario lacks.

  • ✗

    Value engineering

    Why it's wrong here

    Value engineering deliberately reduces cost while preserving required function, so it removes scope rather than adding it. It is tempting because both concern deliverable content, but value engineering is initiated to cut expense against defined requirements, whereas this team added unapproved features.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.