easyMultiple ChoiceObjective-mapped
PK0-005 Practice Question: Based on the change request log exhibit, what…
Network Topology
Based on the change request log exhibit, what should the project manager do next regarding the change requests?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Process CR-01 through the change control board
CR-01 is submitted with high priority, so the project manager should ensure it is reviewed and processed by the change control board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Reject CR-01 to avoid scope creep
Why it's wrong here
CR-01 has not been evaluated yet; should be reviewed.
- ✗
Implement CR-02 and CR-03 immediately
Why it's wrong here
Approved changes should be implemented, but the focus should be on the pending high-priority CR-01 first.
- ✓
Process CR-01 through the change control board
Why this is correct
A submitted high-priority CR needs to be evaluated by the CCB.
- ✗
Inform the requester that CR-04 was rejected
Why it's wrong here
This is already done; the log shows it's rejected.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.