PK0-005 Practice Question: Based on the change request log exhibit, what…
Network Topology
Based on the change request log exhibit, what should the project manager do next regarding the change requests?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Process CR-01 through the change control board
CR-01 is submitted with high priority, so the project manager should ensure it is reviewed and processed by the change control board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Reject CR-01 to avoid scope creep
Why it's wrong here
Rejecting CR-01 pre-empts the change control process; the log requires each request to be assessed for impact and routed to the CCB before any decision. It is tempting because scope creep is a genuine risk, and rejection would be correct only once analysis shows the change harms the baseline.
- ✗
Implement CR-02 and CR-03 immediately
Why it's wrong here
Implementing CR-02 and CR-03 immediately bypasses the CCB approval step recorded in the change log, so neither request has been authorised or baselined. It is tempting because both may look beneficial, and immediate implementation would be correct only after the board approves them.
- ✓
Process CR-01 through the change control board
Why this is correct
Routing CR-01 through the change control board satisfies the governance constraint in the stem: any request altering approved scope, schedule or budget needs formal evaluation before implementation. The board assesses impact, risk and resource implications, then authorises, defers or rejects, keeping the change request log's status accurate.
- ✗
Inform the requester that CR-04 was rejected
Why it's wrong here
Telling the requester CR-04 was rejected assumes a decision the log shows has not been made; the request must first be assessed and reviewed by the CCB. It is tempting because it closes the item quickly, and such notification would be correct only after the board formally rejects it.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.