Question 363 of 500
Project Management ConceptseasyMultiple ChoiceObjective-mapped

Quick Answer

The answer is Mitigate, because adding extra resources to the critical path directly reduces the impact of a potential two-week delay. Mitigation is a risk response strategy focused on lowering either the probability or the severity of a risk event, and here the project manager is proactively decreasing the delay’s effect by increasing capacity on the critical path. On the CompTIA Project+ PK0-005 exam, this concept tests your ability to distinguish Mitigate from Accept, Avoid, and Transfer—a common trap is confusing Mitigate with Avoid, but Avoid eliminates the risk entirely (e.g., changing the project scope), while Mitigate only lessens its consequences. A helpful memory tip: think of Mitigate as “making it less bad” without making it go away—like adding a safety net, not removing the tightrope.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is working on a software development project. The team has identified a potential risk that could cause a two-week delay. The project manager decides to add extra resources to the critical path to reduce the impact. Which risk response strategy is being used?

Question 1easymultiple choice
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Mitigate

Adding extra resources to the critical path to reduce the impact of a potential two-week delay is a classic example of the Mitigate risk response strategy. Mitigation aims to reduce the probability or impact of a risk, and here the project manager is proactively reducing the impact by increasing capacity on the critical path. This is not accepting the risk, avoiding it, or transferring it to a third party.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Accept

    Why it's wrong here

    Acceptance involves acknowledging the risk without proactive action.

  • Mitigate

    Why this is correct

    Correct. Adding resources to reduce impact is a mitigation strategy.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Avoid

    Why it's wrong here

    Avoidance involves changing the plan to eliminate the risk.

  • Transfer

    Why it's wrong here

    Transfer shifts risk to a third party, e.g., insurance or contracts.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Cisco often tests the distinction between Mitigate and Avoid, where candidates mistakenly choose Avoid because they think adding resources eliminates the risk, but Avoid requires removing the risk source entirely, not just reducing its impact.

Detailed technical explanation

How to think about this question

In project management, the critical path is the sequence of tasks that determines the project's minimum duration; adding resources to critical path tasks can reduce their duration (crashing) but may introduce new risks like increased cost or communication overhead. The Mitigate strategy is often implemented through contingency reserves or parallel tasking, and it differs from Avoidance which requires changing the project scope or approach entirely. Real-world software projects might use mitigation by adding senior developers to a bottleneck task to shorten the delay, while still accepting that some delay risk remains.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Mitigate — Adding extra resources to the critical path to reduce the impact of a potential two-week delay is a classic example of the Mitigate risk response strategy. Mitigation aims to reduce the probability or impact of a risk, and here the project manager is proactively reducing the impact by increasing capacity on the critical path. This is not accepting the risk, avoiding it, or transferring it to a third party.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Match each risk response strategy to its description.

medium

    Why : These are standard risk response strategies for threats and opportunities.

    Last reviewed: Jun 24, 2026

    Question Discussion

    Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

    Loading comments…

    Sign in to join the discussion.

    This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.