easyMultiple ChoiceObjective-mapped
PK0-005 Practice Question: A project manager is working on a software…
A project manager is working on a software development project. The team has identified a potential risk that could cause a two-week delay. The project manager decides to add extra resources to the critical path to reduce the impact. Which risk response strategy is being used?
⚠ Common exam trap
The PK0-005 exam often tests the distinction between Mitigate and Avoid, where candidates mistakenly choose Avoid because they think adding resources eliminates the risk, but Avoid requires removing the risk source entirely, not just reducing its impact.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Mitigate
Adding extra resources to the critical path to reduce the impact of a potential two-week delay is a classic example of the Mitigate risk response strategy. Mitigation aims to reduce the probability or impact of a risk, and here the project manager is proactively reducing the impact by increasing capacity on the critical path. This is not accepting the risk, avoiding it, or transferring it to a third party.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Accept
Why it's wrong here
Acceptance involves acknowledging the risk without proactive action.
- ✓
Mitigate
Why this is correct
Correct. Adding resources to reduce impact is a mitigation strategy.
- ✗
Avoid
Why it's wrong here
Avoidance involves changing the plan to eliminate the risk.
- ✗
Transfer
Why it's wrong here
Transfer shifts risk to a third party, e.g., insurance or contracts.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.