Courseiva
Tools and DocumentationhardMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

A project has a BAC of $100,000. The earned value is $40,000, actual cost is $50,000, and planned value is $30,000. What is the estimate at completion (EAC) assuming the current cost performance is expected to continue?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

$125,000

EAC = BAC/CPI. CPI = EV/AC = 40,000/50,000 = 0.8. So EAC = 100,000/0.8 = $125,000. This reflects that the project will likely exceed the original budget.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • $110,000

    Why it's wrong here

    110,000 might be AC + (BAC - EV) = 50,000 + 60,000, but that's for atypical variance.

  • $75,000

    Why it's wrong here

    75,000 might be BAC - EV, not correct for this formula.

  • $90,000

    Why it's wrong here

    90,000 does not come from standard EAC calculation.

  • $125,000

    Why this is correct

    Correct. EAC = BAC/CPI = 100,000/0.8 = 125,000.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.