PK0-005 Practice Question: A project manager is identifying stakeholders and…
A project manager is identifying stakeholders and documenting their interests and influence. In which project life cycle phase is this activity performed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Initiating
Identifying stakeholders is a key activity in the Initiating phase, where the project is formally authorized and stakeholders are identified.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Executing
Why it's wrong here
Executing involves performing the work, not initial identification.
- ✓
Initiating
Why this is correct
Identifying stakeholders is part of the Initiating phase.
- ✗
Closing
Why it's wrong here
Closing involves finalizing all activities, not identification.
- ✗
Planning
Why it's wrong here
Planning involves detailed project planning, not initial stakeholder identification.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.