Courseiva
Project Management ConceptsmediumMultiple SelectObjective-mapped

PK0-005 Project Management Concepts Practice Question

A project manager is reviewing the project selection methods for a new initiative. Which TWO of the following are financial project selection methods? (Choose two.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Net Present Value (NPV)

Net Present Value (NPV) and Internal Rate of Return (IRR) are financial methods used to evaluate project profitability.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • SWOT analysis

    Why it's wrong here

    SWOT is a strategic analysis tool, not a financial selection method.

  • Expert judgment

    Why it's wrong here

    Expert judgment is a technique, not a financial method.

  • Net Present Value (NPV)

    Why this is correct

    NPV is a financial method.

  • Internal Rate of Return (IRR)

    Why this is correct

    IRR is a financial method.

  • Requirements gathering

    Why it's wrong here

    Requirements gathering is part of planning.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.