PK0-005 Tools and Documentation Practice Question
Which document is used to track and manage changes to the project baseline?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Change log
The change log records all changes and their status, helping manage baseline changes.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Risk register
Why it's wrong here
Risk register tracks risks, not changes.
- ✗
Issue log
Why it's wrong here
Issue log tracks problems, not changes.
- ✓
Change log
Why this is correct
Change log records all change requests and their disposition.
- ✗
Communication plan
Why it's wrong here
Communication plan defines how information is shared, not change tracking.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.