PK0-005 Tools and Documentation Practice Question
Which document is used to track and manage changes to the project baseline?
⚠ Common exam trap
PK0-005 often tests the confusion between the change log and the issue log, since both track items over time; the key differentiator is that the change log specifically tracks modifications to the baseline, while the issue log tracks problems and action items.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Change log
The change log is the document used to track and manage changes to the project baseline, recording each change request, its status, approval, and impact on scope, schedule, or cost. It provides an audit trail of all approved and rejected changes, ensuring the baseline remains controlled. This aligns with the Perform Integrated Change Control process in PMBOK.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Risk register
Why it's wrong here
The risk register records identified risks, their probability, impact and responses; it holds no baseline change requests or approval status. It would be the right artefact when logging and tracking project threats and their mitigation actions throughout the project lifecycle.
- ✗
Issue log
Why it's wrong here
The issue log tracks problems and their resolution, not requested modifications to scope, schedule or cost baselines. It would be correct when recording and monitoring unresolved project problems, owners and target resolution dates rather than controlling baseline changes.
- ✓
Change log
Why this is correct
The change log records every requested change to the project baseline, including approvals, rejections and their outcomes. It provides the audit trail needed to track and manage baseline changes, which is precisely what the question asks for.
- ✗
Communication plan
Why it's wrong here
The communication plan defines who receives which project information, when and by what method; it does not record or approve baseline changes. It would be the correct document when planning stakeholder information distribution, reporting frequency and escalation paths.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official CompTIA exam blueprint
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.